BRC Academy · Contracts

Ready-for-Takeover vs Substantial Performance

An Ontario project on CCDC 2-2020 has two "done" dates, and they come from two different places. Substantial Performance is a statutory test in the Construction Act that starts the lien and holdback clocks. Ready-for-Takeover is a contract milestone that decides whether the contractor finished on time. Owners who treat them as the same date lose money on one side or leverage on the other.

Learning outcomes

  • Apply the section 2 test for substantial performance under Ontario's Construction Act, including the cost-to-complete thresholds.
  • Explain how a certificate of substantial performance is issued and published under section 32, and what publication starts.
  • List the Ready-for-Takeover prerequisites in CCDC 2-2020 GC 12.1 and the Consultant's review timing.
  • Plan both milestones for Northgate's M9 date, Friday January 14, 2028, including what happens if they separate.

The lesson

Two milestones, two sources of law

Substantial Performance belongs to the statute. In Ontario it is defined in section 2 of the Construction Act, R.S.O. 1990, c. C.30, and no contract can change the test. Ready-for-Takeover belongs to the contract. It was introduced in CCDC 2-2020, as lesson 6 explained, and the parties can adjust it through Supplementary Conditions. CCDC 2-2020 makes Substantial Performance the first prerequisite of Ready-for-Takeover, so Ready-for-Takeover can never come first. It can come on the same day, or later.

Ready-for-Takeover contains Substantial Performance An outer box for Ready-for-Takeover under GC 12.1 holds six prerequisites. The first is Substantial Performance under the Construction Act. The others are occupancy requirements met, final cleaning and waste removal, as-built drawings and operation and maintenance data, start-up testing with training scheduled, and the owner able to secure access. Below, Substantial Performance publication starts the lien period and holdback release, while Ready-for-Takeover meets Contract Time and starts the warranty, insurance and waiver clocks. Ready-for-Takeover (CCDC 2-2020, GC 12.1) 1. Substantial Performance Construction Act s. 2 test, certified under s. 32 2. Occupancy requirements met (permit or evidence) 3. Final cleaning and waste removal done 4. As-built drawings on site; O&M data delivered 5. Start-up testing done; training scheduled 6. Owner can secure access to the Work Changing this list requires a Supplementary Condition. Published SP certificate • 60-day lien period• Basic holdback release• Holdback on later work Ready-for-Takeover • Contract Time met• Warranty starts (GC 12.3)• Insurance, waiver clocks
Figure 1. Ready-for-Takeover contains Substantial Performance plus five further conditions, and each milestone starts different clocks. Prerequisites paraphrased. Source: BRC, based on CCDC 2-2020 GC 12.1 as summarized by Gowling WLG and Torkin Manes, and the Construction Act, ss. 2, 31 and 32.

The statutory test: section 2

Under section 2(1) of the Construction Act, a contract is substantially performed when two things are true. First, the improvement, or a substantial part of it, is "ready for use or is being used for the purposes intended". Second, it can be completed, or known defects corrected, for no more than a set amount: 3% of the first $1,000,000 of the contract price, 2% of the next $1,000,000, and 1% of the balance. These tiers have applied since the October 2019 amendments.

Two other rules sit in the same section. Under section 2(2), if the improvement is ready for use but the owner and contractor agree that some work will not be finished promptly, the value of that work is deducted from the contract price before the test is applied. Under section 2(3), a contract is deemed completed when the remaining cost to finish, correct a known defect or make the last supply is no more than the lesser of 1% of the contract price and $5,000. Completion matters because it starts the lien period for work done after substantial performance.

Notice what the test does not ask. It does not require an occupancy permit, operating manuals, training or a clean building. A warehouse can pass section 2 with a long deficiency list and no permission to occupy, as long as it is usable for its purpose and the list is cheap enough.

Certificate and publication: section 32

Section 32 sets the procedure. The contractor applies to the payment certifier, which on a CCDC 2 project is normally the Consultant. If there is no payment certifier, the owner and contractor decide together. The payment certifier determines whether the contract is substantially performed and, if it is, signs a certificate in the prescribed form showing the date of substantial performance. It must give copies to the owner and contractor within seven days of signing.

The contractor then publishes the certificate. If it has not done so within seven days of receiving it, any person may publish it. Publication is not a formality: a certificate has no effect until it is published. Since January 1, 2026, the regulation designates Daily Commercial News, Link2Build and Ontario Construction News for publishing statutory notices. If the payment certifier refuses unreasonably, a court can make a declaration of substantial performance, and section 32(3) makes a person who unreasonably refuses to certify liable for resulting damages.

What publication starts

Under section 31(2), liens for work supplied up to substantial performance expire 60 days after the earlier of publication of the certificate and completion, abandonment or termination of the contract. Once that period passes with no lien preserved, the owner releases the basic holdback that remains (section 26). Work done after substantial performance carries its own 10% holdback under section 22(2), and its lien period runs from completion.

The 2026 amendments added a twist. Contracts entered into on or after January 1, 2026 must release accrued holdback annually: the owner publishes a notice within 14 days after each contract anniversary and pays 60 to 74 days later unless liens are preserved. The old notice of non-payment of holdback was repealed. Substantial performance still releases the remaining balance.

The contract test: Ready-for-Takeover under GC 12.1

GC 12.1.1 lists the Ready-for-Takeover prerequisites shown in Figure 1. The contractor applies in writing to both the Owner and the Consultant, with a list of items still to be completed or corrected. The Consultant has 10 days from receipt to confirm the date in writing or to say, with reasons, why the Work is not ready. Under GC 12.1.2, a prerequisite delayed by causes beyond the contractor's reasonable control, or by agreement, does not hold Ready-for-Takeover back. The parties then set a reasonable date to finish the listed items.

Ready-for-Takeover is where the contract's money and risk turn over. Contract Time is met. The warranty in GC 12.3 starts. Insurance under GC 11.1 runs to it, and the indemnity and waiver periods in GC 13 are counted from it. If the owner needs to move in earlier, GC 12.2 allows early occupancy of all or part of the Work, with the contractor's agreement (not unreasonably withheld) and approval of the authorities having jurisdiction. The occupied part is treated as taken over, care of it passes to the owner and its warranty starts on occupancy.

Substantial PerformanceReady-for-Takeover
SourceConstruction Act, s. 2CCDC 2-2020, GC 12.1
Can the parties change it?NoYes, by Supplementary Condition
TestUsable, and cheap enough to finishSP plus occupancy, cleaning, documents, testing, access
Who decidesPayment certifier (s. 32)Consultant, within 10 days
Made effective byPublication of the certificateConsultant's written confirmation
What it startsLien period, holdback releaseContract Time met, warranty, insurance and waiver clocks

Northgate worked example

Northgate Distribution Centre (fictional) is a 12,000 m² tilt-up warehouse in Vaughan for Northgate Logistics Inc. (fictional). The CCDC 2-2020 contract with Halvorsen Builders Ltd. (fictional) is $34,950,000 excluding HST, and Ridgeline Architects Inc. (fictional) is the Consultant and payment certifier. The owner's master schedule targets both milestones on the same day: M9, Friday January 14, 2028. The owner's separate racking contractor starts on Monday January 17, 2028 (M10). See the Northgate fact sheet.

How much can be left at substantial performance?

Figure 2 applies the section 2(1) tiers to the original Contract Price. On approved changes the figure moves; the owner's representative should recalculate it on the current price when Halvorsen applies.

Northgate cost-to-complete limit for substantial performance Horizontal bars for a $34,950,000 contract price. Three percent of the first one million is $30,000. Two percent of the next one million is $20,000. One percent of the remaining $32,950,000 is $329,500. The maximum cost to complete or correct is $379,500. The deemed completion limit is $5,000. Contract Price $34,950,000 (excl. HST) 3% of first $1M$30,000 2% of next $1M$20,000 1% of last $32.95M$329,500 Maximum to finish$379,500 Deemed completion$5,000 cap
Figure 2. The most Northgate's remaining and corrective work can cost at substantial performance, under s. 2(1), compared with the s. 2(3) deemed completion limit (the lesser of 1% and $5,000). Bars to scale. Source: BRC calculation from the Construction Act, s. 2, and the Northgate fact sheet.
View the data
TierPrice in tierRateAmount
First$1,000,0003%$30,000
Next$1,000,0002%$20,000
Balance$32,950,0001%$329,500
Total limit for substantial performance$34,950,000$379,500
Deemed completion limit, s. 2(3)lesser of 1% and $5,000$5,000

So when Halvorsen applies, Ridgeline needs a priced list of incomplete and defective work. If the list is worth more than $379,500, the contract is not substantially performed, however close the building looks.

The planned sequence

Figure 3 shows the owner's plan if everything goes well. Halvorsen applies for both milestones on Monday January 10, 2028. Ridgeline inspects, signs the certificate dated January 14 and confirms Ready-for-Takeover the same day, inside its 10-day window, which would have closed on Thursday January 20. Halvorsen publishes the certificate on Tuesday January 18.

Northgate close-out timeline, January 2028 to January 2029 A vertical sequence of dates. January 10, 2028: Halvorsen applies for the certificate and Ready-for-Takeover. January 14: M9, substantial performance certified and Ready-for-Takeover confirmed. January 17: M10, owner's racking install starts. January 18: certificate published. March 18: lien period expires. March 20: basic holdback paid if no liens. March 31: M11, final completion. May 30: lien period for later work expires. January 14, 2029: one-year warranty ends. Not to scale. Dates in 2028 unless shown. Mon Jan 10 Halvorsen appliesSP certificate (s. 32) and RFT (GC 12.1) Fri Jan 14 M9: SP certified, RFT confirmedRidgeline signs; warranty starts Mon Jan 17 M10: racking install startsOwner's separate contract Tue Jan 18 Certificate published60-day lien period starts Sat Mar 18 Lien period expires60 days after publication (s. 31) Mon Mar 20 Basic holdback paidAfter a lien search shows no liens Fri Mar 31 M11: final completionDeficiencies closed Tue May 30 Lien period for later work ends60 days after completion Sun Jan 142029 One-year warranty ends12 months after RFT (GC 12.3)
Figure 3. Northgate's planned close-out sequence if both milestones land on M9. Dates after January 14 are illustrative; the owner's lawyer confirms statutory deadlines. Source: BRC, based on the Northgate fact sheet, the Construction Act and CCDC 2-2020 GC 12.
View the data
DateEventRule
Mon Jan 10, 2028Halvorsen applies for the certificate and Ready-for-Takeovers. 32; GC 12.1
Fri Jan 14, 2028M9: substantial performance certified; Ready-for-Takeover confirmeds. 2; GC 12.1
Mon Jan 17, 2028M10: owner's racking installation startsOwner's separate contract
Tue Jan 18, 2028Certificate publisheds. 32
Sat Mar 18, 2028Lien period for work to substantial performance expiress. 31(2)
Mon Mar 20, 2028Remaining basic holdback paid if no liens preserveds. 26
Fri Mar 31, 2028M11: final completions. 2(3)
Tue May 30, 2028Lien period for work after substantial performance expiress. 31(2)
Sun Jan 14, 2029One-year warranty endsGC 12.3

The holdback at stake is large. At 10% of the Contract Price, the full holdback is $3,495,000 before changes. Because the contract was signed on January 11, 2027, after the 2026 amendments, the first annual-release anniversary is Tuesday January 11, 2028, three days before M9. The owner's lawyer has to decide how the annual-release notice and the substantial performance release will run together so the owner neither pays twice nor misses a deadline.

What if the milestones separate?

Suppose the building passes section 2 on January 14 but the City of Vaughan has not yet accepted the ESFR sprinkler system, so the occupancy prerequisite fails. Ridgeline can certify substantial performance, and the lien clock starts. But Ridgeline must refuse Ready-for-Takeover, with reasons, and Halvorsen is late unless the delay is beyond its reasonable control under GC 12.1.2. The owner's racking start on January 17 is now at risk. The owner can ask for early occupancy of the warehouse under GC 12.2, but only with the City's approval, and the occupied area's warranty and care pass to the owner from that day.

Owner's move

  • Plan two milestones in the schedule. Show Substantial Performance and Ready-for-Takeover as separate milestones, even if planned for the same day, with the RFT prerequisites as predecessor activities.
  • Price the deficiency list early. Ask for a priced list a month before the application so the section 2 threshold is never a surprise.
  • Track publication, not signature. The lien period runs from publication. Get a copy of the published notice and diarize 60 days from it.
  • Run a lien search before releasing holdback. Pay promptly when the period ends, but only after the search.
  • Decide early occupancy before you need it. If racking cannot wait, agree the terms and get the City's approval in advance.

Common mistakes

  1. Treating the signed certificate as effective. Until it is published, it does nothing.
  2. Measuring liquidated damages from substantial performance. Under CCDC 2-2020, the contractor is on time only at Ready-for-Takeover.
  3. Letting the Consultant's 10 days lapse. The Consultant must confirm or give written reasons; silence invites a dispute.
  4. Moving in without GC 12.2 terms. Informal occupancy blurs who has care of the Work and when the warranty starts.
  5. Forgetting the second lien period. Work done after substantial performance has its own holdback and its own clock.

Quick quiz

  1. Northgate's remaining and corrective work is priced at $420,000 on a $34,950,000 contract. Is the contract substantially performed under section 2(1)?

    1. Yes, it is under 3% of the price
    2. No, it exceeds the $379,500 limit
    3. Yes, if the Consultant agrees
    4. Only if the owner has moved in
  2. When does a certificate of substantial performance take effect?

    1. When the payment certifier signs it
    2. When copies reach the owner and contractor
    3. When it is published
    4. Sixty days after signing
  3. Who normally publishes the certificate first?

    1. The owner
    2. The contractor
    3. The City
    4. The lender
  4. How long does the Consultant have to respond to a Ready-for-Takeover application under GC 12.1?

    1. 5 days
    2. 7 days
    3. 10 days
    4. 28 days
  5. Which of these is a Ready-for-Takeover prerequisite but not part of the section 2 test?

    1. The building is ready for its intended use
    2. Cost to complete is under the threshold
    3. Occupancy requirements are met
    4. A payment certifier exists
Show answers and explanations
  1. B. The tiers give $30,000 + $20,000 + $329,500 = $379,500. At $420,000, the test fails.
  2. C. Section 32 says the certificate has no effect until it is published.
  3. B. The contractor publishes; if it does not within seven days of receiving it, any person may.
  4. C. The Consultant has 10 days to confirm the date or give written reasons why the Work is not ready.
  5. C. Occupancy is a contract prerequisite in GC 12.1; the statute only asks about use and cost to complete.

Key terms

Substantial performance
The Construction Act, s. 2 milestone: the improvement is usable for its purpose and can be finished within the cost thresholds.
Payment certifier
The architect, engineer or other person whose certificate triggers payment under the contract; on CCDC 2, normally the Consultant.
Certificate of substantial performance
The prescribed form signed under s. 32, effective only once published.
Construction trade newspaper
A publication designated for statutory notices; currently Daily Commercial News, Link2Build and Ontario Construction News.
Lien period
The 60 days after publication or completion during which a lien must be preserved, under s. 31.
Deemed completion
Under s. 2(3), completion when the remaining cost is no more than the lesser of 1% of the price and $5,000.
Ready-for-Takeover
The CCDC 2-2020 GC 12.1 milestone: substantial performance plus occupancy, cleaning, documents, testing and access.

References

  1. Government of Ontario, Construction Act, R.S.O. 1990, c. C.30, ss. 2, 22, 26, 31 and 32 (e-Laws).
  2. Consolidated Construction Act, industry-hosted consolidation (used to read ss. 2, 22, 26, 31 and 32; check against e-Laws).
  3. Ontario Association of Architects, Certifying substantial performance (2020).
  4. Gowling WLG, What the new CCDC 2 stipulated price contract means for you (December 2020).
  5. Torkin Manes LLP, Canadian construction contracts: welcome to the new CCDC 2 (2020) (February 2021).
  6. Fasken, Ontario's amendments to the Construction Act take effect January 1, 2026 (December 2025).
  7. DLA Piper, Critical amendments to Ontario Construction Act have arrived (January 2026).
  8. Miller Thomson LLP, Substantial performance: what you need to know (November 2019).

Verified on November 4, 2026.

Next lesson in this trackCCDC 3 cost-plus: controlling the Cost of the Work

This lesson is general education, not legal advice. Get advice from a construction lawyer on your contract.

PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. Oracle and Primavera are trademarks of Oracle. Microsoft Project is a trademark of Microsoft. BRC Academy is not affiliated with or endorsed by these organizations.

← All BRC Academy lessons

Have a program that's slipping, or about to start?

Book a 30-minute call. We'll tell you where your schedule and budget are exposed, and what an owner's rep would change, before you commit to anything.