What's moving construction budgets in Toronto.
The public numbers that matter to owners, in one place, with what they mean for your program. Updated November 25, 2026.
Toronto construction costs keep climbing for commercial work
Building construction price index, Toronto (2023 = 100)
View the data
| Quarter | Non-residential | Residential |
|---|---|---|
| Q1 2025 | 106.7 | 105.4 |
| Q2 2025 | 108.2 | 105.6 |
| Q3 2025 | 109.1 | 105.9 |
| Q4 2025 | 109.6 | 106.4 |
| Q1 2026 | 110.3 | 106.5 |
| Q2 2026 | 111.9 | 105.8 |
| Q3 2026 | 113.0 | 106.2 |
What it means for owners
- Carry escalation separately from contingency. Commercial construction costs in Toronto rose 3.6% in a year. For work starting in 2027, a 3% to 4% escalation allowance is a defensible starting point. Don't let it quietly eat your contingency.
- Residential is flat, and that's an opening. Toronto residential costs rose just 0.3% in a year, and last quarter's 0.4% gain was among the smallest in the country. Trades that depend on housing are looking for work, which can mean sharper commercial tenders right now.
Borrowing costs are rising again
Canadian prime business rate (%)
View the data
| Effective (week of) | Prime rate |
|---|---|
| Jul 2023 | 7.20% |
| Jun 2024 | 6.95% |
| Jul 2024 | 6.70% |
| Sep 2024 | 6.45% |
| Oct 2024 | 5.95% |
| Dec 2024 | 5.45% |
| Feb 2025 | 5.20% |
| Mar 2025 | 4.95% |
| Sep 2025 | 4.70% |
| Nov 2025 | 4.45% |
| Nov 2026 | 4.70% |
What it means for owners
- Price your delay, not just your build. At a 4.70% prime rate, carrying $20 million of project financing costs roughly $78,000 a month in interest alone, before holdover rent or lost revenue. The Bank of Canada raised rates in October and says further increases could be needed, so that number belongs in every schedule recovery decision.
Fuel is the cost driver to watch
Statistics Canada industrial product prices, October 2026
What it means for owners
- Watch equipment-heavy scopes. Statistics Canada says higher material, fuel, transportation and labour costs drove the latest construction cost increases, and diesel is up 93.3% in a year. Before you sign, check how your contracts treat fuel and material escalation.
- Tariffs still matter. Retaliatory tariffs of 15% to 50%, including 50% on certain steel and aluminum products, took effect September 8, 2026. Ask bidders how much tariff exposure is in their steel and metals pricing.
Is your budget exposed?
Test your own program with the owner's rep ROI calculator, or book a 30-minute call and we'll walk through your escalation, contingency and schedule risk.
Sources: Statistics Canada, Building construction price indexes, third quarter 2026 (Table 18-10-0289-01), with earlier quarters from the second quarter 2026, first quarter 2026 and fourth quarter 2025 releases (earlier quarters may since have been revised); Statistics Canada, Industrial product and raw materials price indexes, October 2026; Bank of Canada, policy rate announcement, October 28, 2026 and interest rates. The financing example is illustrative. This page is general information, not financial or legal advice. Next update in December 2026, after the Bank of Canada's December 9 rate decision and Statistics Canada's November industrial price release.