BRC Academy · Case study

Northgate Distribution Centre (fictional case study)

Northgate Distribution Centre is a fictional project. It is the single case study used in every BRC Academy lesson, so each contract clause, schedule, cost report and claim builds on the same facts. Northgate Logistics Inc. is also fictional. Any resemblance to a real project or company is coincidental.

Lessons cite this page as "the Northgate fact sheet". When a lesson adds a fact, such as a delay event or a change order, it is added here so the story stays consistent.

Scope

ProjectNorthgate Distribution Centre (project code NDC), Vaughan, Ontario
OwnerNorthgate Logistics Inc. (fictional), a private owner-occupier, with an owner's project manager and an owner's representative
Building12,000 m² single-storey tilt-up concrete warehouse with a 9.75 m (32 ft) clear height and ESFR sprinklers
Office900 m² two-level office mezzanine at the front of the building
Loading14 dock doors and 2 drive-in doors
Site2.6 ha

Contract and team

Delivery methodDesign-bid-build
Construction contractCCDC 2-2020 stipulated price contract, with the owner's Supplementary Conditions
General contractorHalvorsen Builders Ltd. (fictional)
Prime consultantRidgeline Architects Inc. (fictional), under an OAA 600 agreement, with structural and MEP subconsultants
SchedulesThe GC submits its schedule in Oracle Primavera P6 (XER files). The owner's master schedule is kept in Microsoft Project desktop.
Work weekMonday to Friday, 8 hours a day, with Ontario statutory holidays as non-working days

Budget

Northgate construction budget of $38.0 million Contract Price $34.95 million, 92 per cent; owner construction contingency $3.05 million, 8 per cent. Construction budget: $38.0M (excl. HST) Contract Price $34.95M 92% stipulated price to the GC (CCDC 2-2020) Contingency $3.05M (8%) Holdback of 10% is retained from each payment under the Ontario Construction Act.
Figure 1. Northgate construction budget. Source: BRC, Northgate fact sheet (fictional).
View the data
ItemAmount (excl. HST)Share
Contract Price$34,950,00092%
Owner construction contingency$3,050,0008%
Construction budget$38,000,000100%

Key milestones (baseline)

Tender closed on Tuesday, December 8, 2026. The owner's master schedule starts at contract execution; the contractor's schedule starts at mobilization.

Northgate baseline milestones, January 2027 to March 2028 Twelve milestones from contract execution on January 11, 2027 to final completion on March 31, 2028. Ready-for-Takeover and Substantial Performance is targeted for January 14, 2028. Jan 2027 Apr Jul Oct Jan 2028 Apr M0 Contract executed Jan 11 M1 Kickoff meeting Jan 19 M2 Building permit issued Feb 26 M3 Site mobilization Mar 1 M4 Foundations and slab complete May 14 M5 Tilt-up panels erected Jun 25 M6 Roof complete, weathertight Sep 3 M7 Permanent power Oct 1 M8 Commissioning starts Nov 1 M9 Ready-for-Takeover / SP Jan 14 M10 Racking and occupancy start Jan 17 M11 Final completion Mar 31
Figure 2. Northgate baseline milestones. M9 (orange) is the contractual completion target. Source: BRC, Northgate fact sheet (fictional).
View the data
IDMilestoneDate
M0Contract executedMon Jan 11, 2027
M1Kickoff meetingTue Jan 19, 2027
M2Building permit issuedFri Feb 26, 2027
M3Site mobilizationMon Mar 1, 2027
M4Foundations and slab completeFri May 14, 2027
M5Tilt-up panels erectedFri Jun 25, 2027
M6Roof complete, weathertightFri Sep 3, 2027
M7Permanent powerFri Oct 1, 2027
M8Commissioning startsMon Nov 1, 2027
M9Ready-for-Takeover / Substantial PerformanceFri Jan 14, 2028
M10Racking and occupancy startMon Jan 17, 2028
M11Final completionFri Mar 31, 2028

Summary WBS

Northgate summary work breakdown structureLevel 1 is the project NDC. Level 2 has ten elements, from project management and pre-construction to closeout. NDC Northgate DC 1 Project management & pre-construction 2 Sitework & services 3 Foundations & slab-on-grade 4 Structure: tilt-up panels, steel, joists, deck 5 Roofing & envelope 6 Office mezzanine & interiors 7 Mechanical, electrical & fire protection 8 Dock doors & equipment 9 Commissioning & turnover 10 Closeout
Figure 3. Northgate summary work breakdown structure (level 2). Source: BRC, Northgate fact sheet (fictional).

Change log

  • v1, November 4, 2026: first issue.

Northgate Distribution Centre, Northgate Logistics Inc., Halvorsen Builders Ltd. and Ridgeline Architects Inc. are fictional and are used for teaching only.

Oracle and Primavera are trademarks of Oracle. Microsoft Project is a trademark of Microsoft. BRC Academy is not affiliated with or endorsed by these organizations.

← BRC Academy