BRC Academy · Construction Phase

Ontario OHSA: owner vs constructor duties

Ontario's Occupational Health and Safety Act (OHSA) does not let an owner hand off all safety risk by signing a construction contract. The Act gives the widest project duties to one party, the constructor, but it also places duties on the owner that no contract can transfer. This lesson covers who the constructor is, what the owner still owes, and a 2023 Supreme Court of Canada decision that changed how owners should act on site.

Learning outcomes

  • Explain the OHSA meanings of owner, constructor and project, and test who the constructor is on a given set of facts.
  • List the constructor's general duties under section 23 and the owner's duties under sections 29 and 30.
  • Describe the owner's designated substances duty, when the list is due, and the liability for leaving a substance off it.
  • Explain what R. v. Greater Sudbury (City) means for owners who use a general contractor as constructor.

The lesson

Three definitions that decide everything

Section 1(1) of the OHSA sets the vocabulary. An owner is read widely: it includes trustees, receivers, mortgagees in possession, tenants, lessees and occupiers of the lands, and anyone acting as the owner's agent or delegate. A project is, broadly, a construction project. A constructor is a person who undertakes a project for an owner, and the definition also catches an owner who undertakes all or part of a project alone or with more than one employer. "Undertakes" means taking on responsibility for the project.

The practical rule follows: every project has a constructor, and if no one else has taken the role, the owner likely has it.

How an owner becomes the constructor

The province's constructor guideline covers the common cases. If the owner contracts with one contractor for all the work, that contractor is the constructor, even if it subcontracts most of the work. If the owner hires several contractors and does not designate one of them, the owner will likely be treated as the constructor. If one contractor, or a third party, accepts the role and the owner gives up control, that party is the constructor even though the owner pays the others directly.

Two details matter for owner-side PMs. First, an owner whose own employees work on a general contractor's site can become the constructor if the contractor did not agree to those workers and does not direct them. Second, section 1(3) says that an owner who engages an architect, engineer or other person solely to oversee quality control does not, by that alone, become the constructor. That protects the normal owner's representative and consultant model, as long as the oversight stays on quality and compliance with the contract.

Ministry inspectors decide who the constructor is from the facts on site. A contract clause is strong evidence, but an owner who behaves like the constructor can be found to be one.

Who is the constructor? A decision flow Start with the owner beginning a project. Question 1: does one contractor do all the work under one contract? If yes, it is the constructor even if it subcontracts. If no, question 2: has one party accepted the constructor role in writing and does it control the work? If yes, that party is the constructor even if the owner pays the others. If no, the owner is likely the constructor. Three checks apply in every case: the owner's own workers, quality-control inspections under section 1(3), and the fact that inspectors decide on the facts. Owner starts a project 1. Does one contractor do all the work under one contract? Yes It is the constructor, even if it subcontracts No 2. Has one party accepted the constructor role in writing, and does it control the work? Yes That party is the constructor, even if the owner pays the others No The owner is likely the constructor Checks that apply in every case Owner's own workers on site that the constructor has not agreed to direct can make the owner constructor. Hiring an architect or engineer only for quality control does not, on its own, do so (s. 1(3)). An inspector decides on the facts found on site, not on the contract wording alone.
Figure 1. A simple test for who the constructor is. Real cases turn on the facts, so treat this as a screening tool, not an answer. Source: BRC, based on OHSA s. 1 and the Ontario constructor guideline.

What the constructor must do: section 23

Section 23(1) gives the constructor three general duties on the project: make sure the measures and procedures the Act and regulations prescribe are carried out; make sure every employer and every worker on the project complies with the Act and regulations; and make sure the health and safety of workers on the project is protected. Section 23(2) adds that, where a regulation requires it, the constructor must notify the Ministry before work begins. For construction that means the Notice of Project under O. Reg. 213/91, covered in lesson 7.

The construction regulation adds specific constructor duties on top, such as appointing a supervisor for any project where five or more workers will work at the same time, and setting written emergency procedures. The constructor also reports deaths, critical injuries and certain other occurrences to the Ministry. These are the duties an owner pays a general contractor to carry.

What the owner still owes: sections 29 and 30

Section 29 is the general owner duty. Under s. 29(1), the owner must provide and maintain prescribed facilities, make sure the workplace complies with the regulations, and make sure no workplace is built, altered or added to except in compliance with the Act and regulations. Where a regulation requires it, the owner must also give the Ministry drawings, plans or specifications.

Section 30 is the one owners most often miss. Before a project begins, the owner must find out whether any designated substances are present at the project site and prepare a list of them. If the owner tenders the work, the list must be part of the tender information. Under s. 30(3) the owner must give the constructor the list before a binding contract, and under s. 30(4) the constructor must pass it to each prospective contractor and subcontractor before they sign. Section 30(5) makes an owner who fails these duties liable to the constructor, contractors and subcontractors for losses caused by a designated substance the owner ought reasonably to have known about but did not list.

The designated substances are a short prescribed set that includes asbestos, lead, mercury and silica. On an existing building the list comes from a hazardous materials survey; on a vacant site it may say none were found, but it must still be issued.

Owner and constructor duties under the OHSA, side by side Two columns. Owner: section 29(1) keep facilities compliant and build or alter only in compliance; section 30 find and list designated substances before the project; put the list in the tender and give it to the constructor before the contract; section 30(5) liability for omitted substances. Constructor: section 23(1)(a), (b) and (c) prescribed measures, compliance of every employer and worker, protection of workers; section 23(2) and 30(4) notify the Ministry where required and pass the list to subcontractors before contract. A band at the bottom notes that either party can also be an employer owing section 25 duties. Owner Constructor s. 29(1) Keep facilities compliant; build or alter only in compliance with the Act s. 30 Before the project begins, find designated substances on site and list them s. 30 and 30(3) Put the list in the tender; give it to the constructor before the contract s. 30(5) Liable for losses from a substance it ought to have known of but left off s. 23(1)(a) Ensure prescribed measures and procedures are carried out on the project s. 23(1)(b) Ensure every employer and worker complies with the Act and regulations s. 23(1)(c) Ensure the health and safety of workers on the project is protected s. 23(2) and 30(4) Notify the Ministry where required; pass the list to subcontractors pre-contract Either party can also be an employer under s. 1(1) and owe s. 25 duties to workers on the project (R. v. Greater Sudbury (City), 2023 SCC 28).
Figure 2. The owner's duties are few but cannot be contracted away; the constructor's are broad. Source: BRC, based on OHSA ss. 23, 29 and 30 as summarized in Ontario's Guide to the OHSA.

The owner can still be an employer: R. v. Greater Sudbury

In 2015 a pedestrian was killed by a road grader on a City of Sudbury water main repair. The City had contracted a paving firm as constructor, but the Ministry also charged the City as an employer.

In November 2023 the Supreme Court of Canada, in a split decision, held that the City was an employer under the OHSA, through its own inspectors on the project and its contract for the constructor's services, and that the Crown did not have to prove the City controlled the workers or the workplace to show a breach of s. 25. Control still matters, but at the second stage, where the owner can argue due diligence: that it took every reasonable precaution in the circumstances.

In 2024 the Ontario Superior Court of Justice upheld the trial finding that the City had been duly diligent and had not taken over the constructor role. The helpful factors are worth copying: a contractor with the safety expertise the City lacked, inspections limited to contract quality, hazards raised with the contractor, and attendance at progress meetings. The City had not used its contract rights to remove workers or stop the work.

The lesson is not to stay away from site. It is to keep evidence that you chose a competent constructor, raised hazards you saw, and left direction of the work to the constructor.

Where the contract fits

CCDC 2-2020 rewrote its health and safety clause (GC 9.4) and does not name the constructor for you, as lesson 3 explained. Owners should name the constructor in the Supplementary Conditions, state that it covers the whole project for its full duration, and say how separate contractors and the owner's own forces will be brought under its control. The stakes are real: Ontario's guide lists maximum fines of $2,000,000 for a corporation and $1,500,000 for a director or officer.

Northgate worked example

Northgate Logistics Inc. (fictional) is building the 12,000 m² Northgate Distribution Centre in Vaughan under a CCDC 2-2020 stipulated price contract with Halvorsen Builders Ltd. (fictional), signed on Monday, January 11, 2027. As set out at kickoff in lesson 3, the owner's Supplementary Conditions name Halvorsen as constructor for the whole project, including the owner's racking installer who starts after Ready-for-Takeover. (See the Northgate fact sheet.)

Section 30. Before tender, Northgate commissioned a designated substances assessment of the vacant 2.6 ha site. It found no designated substances on the site. The report and list went into the tender package, so bidders had them before tender close on Tuesday, December 8, 2026, and the executed contract lists them among Halvorsen's documents. That closes the s. 30(3) duty.

Section 23. Halvorsen runs the safety program, appoints the supervisor, files the Notice of Project and controls every trade from mobilization on Monday, March 1, 2027.

The hard case: racking. Ready-for-Takeover is Friday, January 14, 2028, but Halvorsen's deficiency crews stay on site until final completion on March 31, 2028. Northgate's separate racking contractor starts on Monday, January 17, 2028. Without the SC clause, Northgate would be an owner with two employers on its site at once, which is the fact pattern that makes an owner the constructor. Because Halvorsen has agreed to coordinate and control the racking crew, it stays the constructor. The racking contract makes this practical: the installer must follow Halvorsen's site rules, attend its orientation and complete its own registration before starting.

Owner as employer. The owner's representative and Northgate's facilities staff will walk the site. Following the Sudbury factors, they record what they check (quality and contract compliance), raise any hazard they see to Halvorsen's superintendent in writing the same day, and never instruct a trade directly.

Northgate OHSA roles over time Timeline from December 2026 to March 2028. The owner puts the designated substances list in the tender by December 8, 2026; the contract signed January 11, 2027 names Halvorsen as constructor; Halvorsen files the Notice of Project by February 19, 2027 and is constructor on site from March 1, 2027 to March 31, 2028. Ready-for-Takeover is January 14, 2028, and the owner's racking crew works from January 17 to March 10, 2028 under Halvorsen's control. Jan Apr Jul Oct Jan 2027 2028 Designated substanceslist in tender by Dec 8, 2026 Contract; SC namesHalvorsen constructor Jan 11, 2027 Notice of Projectfiled by Halvorsen Feb 19, 2027 Halvorsen on siteas constructor Mar 1, 2027 to Mar 31, 2028 Ready-for-Takeover Jan 14, 2028 Owner's racking crewunder Halvorsen Jan 17 to Mar 10, 2028
Figure 3. Northgate (fictional) OHSA roles over time. Halvorsen's constructor role covers the overlap with the owner's racking crew after Ready-for-Takeover. Source: BRC, based on the Northgate fact sheet and OHSA ss. 23 and 30.
View the data
ItemDate or periodOHSA link
Designated substances list in tenderBy Tue Dec 8, 2026s. 30
Contract signed; SC names Halvorsen constructorMon Jan 11, 2027s. 1, s. 30(3)
Notice of Project filed by HalvorsenBy Fri Feb 19, 2027s. 23(2)
Halvorsen on site as constructorMon Mar 1, 2027 to Fri Mar 31, 2028s. 23
Ready-for-TakeoverFri Jan 14, 2028None (contract milestone)
Owner's racking crew under Halvorsen's controlMon Jan 17 to Fri Mar 10, 2028s. 1 (constructor definition)

Owner's move

Demand a Supplementary Conditions clause that names the constructor for the whole project and its full duration, including any separate contractors and owner forces, and that requires the constructor to control their access.

Check that the s. 30 list exists, was in the tender, and is listed in the contract documents the constructor received. Review the constructor's safety record before award and keep the review on file.

Reject any plan that puts owner staff or a second contractor on site outside the constructor's control, and any habit of owner staff instructing trades directly. Raise hazards through the constructor, in writing.

Owner's rule: pay the constructor to carry the role, then behave in a way that lets it. Watch, record and raise; do not direct.

Common mistakes

  1. Assuming the contract settles it. An inspector looks at who actually controls the site. A named constructor with an owner who runs its own trades is a weak position.
  2. Forgetting the overlap periods. Early works, owner-supplied equipment installers and post-takeover fit-out all put a second employer on site. Each needs a constructor answer.
  3. No designated substances list on a "clean" site. Section 30 still applies. Issue a list that says what was assessed and found.
  4. Owner inspectors who direct work. After Sudbury, owner staff on site make the owner an employer; directing trades weakens due diligence and can shift the constructor role.

Quick quiz

  1. An owner hires three trade contractors directly and names none of them as constructor. Who is likely the constructor?

    1. The largest trade contractor
    2. The owner
    3. The architect
    4. No one, since there is no general contractor
  2. Which OHSA section requires the owner to list designated substances present at a project before it begins?

    1. Section 23
    2. Section 25
    3. Section 29
    4. Section 30
  3. Under s. 23(1), the constructor must ensure all of the following except:

    1. Prescribed measures and procedures are carried out on the project
    2. Every employer and worker complies with the Act and regulations
    3. The owner's finished building meets the Building Code
    4. The health and safety of workers on the project is protected
  4. The owner hires an engineer only to inspect concrete quality for contract compliance. Under s. 1(3), this:

    1. Makes the owner the constructor
    2. Does not, on its own, make the owner the constructor
    3. Makes the engineer the constructor
    4. Requires a second Notice of Project
  5. What did the Supreme Court decide in R. v. Greater Sudbury (City), 2023 SCC 28?

    1. Owners can never be employers on a project with a constructor
    2. The City was an employer, and control is relevant to due diligence rather than to proving the breach
    3. The contractor was not the constructor
    4. Owners must file the Notice of Project
Show answers and explanations
  1. B. An owner who undertakes a project with more than one employer and no designated constructor is likely to be the constructor.
  2. D. Section 30 covers designated substances on projects. Section 29 sets general owner duties for the workplace, and s. 23 sets constructor duties.
  3. C. Section 23(1) is about worker safety on the project. Building Code compliance is a separate permit and design matter.
  4. B. Quality-control oversight alone does not make the owner the constructor, provided it does not turn into directing the work.
  5. B. The majority held the City was an employer and that control goes to the due diligence defence. The case was sent back, and the City's due diligence defence later succeeded.

Key terms

Owner (OHSA)
A broad term in s. 1(1) that includes trustees, receivers, mortgagees in possession, tenants, lessees, occupiers and anyone acting as the owner's agent or delegate.
Constructor
The person who undertakes a project for an owner, including an owner who undertakes all or part of a project alone or with more than one employer. Each project has one.
Designated substance
One of a short list of hazardous substances prescribed under the OHSA, such as asbestos, lead and silica, that the owner must identify and list before a project begins.
Employer (OHSA)
A person who employs or contracts for the services of workers. After the Sudbury decision, an owner with its own staff on a project can be an employer there.
Due diligence
The defence that a party took every reasonable precaution in the circumstances.

References

  1. Government of Ontario, Occupational Health and Safety Act, R.S.O. 1990, c. O.1, ss. 1, 23, 25, 29, 30 (e-Laws).
  2. Government of Ontario, Guide to the OHSA, Part III: Duties of employers and other persons (updated March 24, 2025).
  3. Government of Ontario, Constructor guideline (updated August 13, 2026).
  4. Government of Ontario, Guide to the OHSA, Part IX: Offences and penalties.
  5. Supreme Court of Canada, Case in Brief: R. v. Greater Sudbury (City), 2023 SCC 28 (November 10, 2023).
  6. Cassels, Due diligence deliverance: court upholds due diligence defence in R. v. Greater Sudbury (2024 ONSC 3959).
  7. Canadian Construction Documents Committee, CCDC 2-2020 Stipulated Price Contract, GC 9.4. See lesson 3 for sources.

Verified on November 4, 2026.

Next lesson in this trackNotice of Project and safety oversight

This lesson is general education, not legal advice. Get advice from a construction lawyer on your contract.

PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. Oracle and Primavera are trademarks of Oracle. Microsoft Project is a trademark of Microsoft. BRC Academy is not affiliated with or endorsed by these organizations.

← All BRC Academy lessons

Have a program that's slipping, or about to start?

Book a 30-minute call. We'll tell you where your schedule and budget are exposed, and what an owner's rep would change, before you commit to anything.