Notice of Project and safety oversight

Before the first excavator arrives, the constructor has to tell Ontario's Ministry of Labour, Immigration, Training and Skills Development that the project exists. The Notice of Project is a short filing, but it is also the first public record of who the constructor is, and it opens a set of start-up safety duties. This lesson covers when the notice is required, what goes in it, the other items that should be on site by day one, and how an owner watches site safety without taking over the constructor's role.

Learning outcomes

  • Test a project against the Notice of Project triggers in section 6 of O. Reg. 213/91.
  • Explain who files the notice, when, what it contains, and how it is posted and kept current.
  • List the other start-up safety items: Form 1000 registration, supervisor, emergency procedures, facilities, and the worker thresholds for a health and safety representative and a joint committee.
  • Set up an owner's safety oversight routine that builds a due diligence record without directing the work.

The lesson

When a Notice of Project is required

Section 6 of O. Reg. 213/91, the Construction Projects regulation under the OHSA, sets the triggers. Meeting any one of them is enough. The Ministry's guidance lists them as:

  • total expected cost of labour and materials over $50,000 (or over $250,000 for a project confined to an automobile manufacturing or assembly factory);
  • erecting or structurally altering a building over two storeys or over 7.5 m high, or demolishing a building at least 4 m high with at least 30 m² of floor area;
  • work on bridges, earth- or water-retaining structures over 3 m high, and silos, chimneys and similar structures over 7.5 m high;
  • compressed air work, and tunnels, caissons, cofferdams or wells that a person may enter;
  • a trench a person may enter that is over 300 m long, or over 1.2 m deep and over 30 m long;
  • building an ice road; and any work the regulation requires a professional engineer to design.

The cost trigger catches almost every commercial building project. The Ministry has consulted on replacing it with hazard-based triggers, so check the current text of s. 6 on e-Laws before relying on any threshold.

Notice of Project trigger check for Northgate Six selected triggers from section 6(1) of O. Reg. 213/91 with Northgate's status. Labour and materials over $50,000: yes. Building over two storeys or 7.5 m high: yes, 9.75 m clear height. Demolition: no. Bridges, tunnels, caissons, compressed air or ice roads: no. Long or deep trenches: check, site services. Work requiring a professional engineer's design: check. Any one trigger is enough; Northgate meets two. SELECTED s. 6(1) TRIGGERS NORTHGATE Labour and materials over $50,000 Northgate: $34.95M Contract Price Yes Building over two storeys or over 7.5 m high Northgate: 9.75 m clear height Yes Demolishing a building at least 4 m high with 30 m² or more Northgate: vacant site No Bridge, tunnel, caisson, cofferdam, compressed air or ice road Northgate: none in scope No Trench over 300 m long, or over 1.2 m deep and over 30 m long Northgate: site services, confirm Check Work the regulation requires a professional engineer to design Northgate: ask Halvorsen Check Any one trigger is enough. Northgate meets two. Halvorsen files before work begins and posts a copy.
Figure 1. Testing Northgate (fictional) against selected Notice of Project triggers. One "yes" settles it; the "check" rows matter for other notices and engineering requirements. Source: BRC, based on O. Reg. 213/91 s. 6(1) as summarized by the Ministry.

Who files, when, and what goes in it

The constructor files, before work on the project begins. Section 23(2) of the OHSA makes notice a constructor duty, and failing to notify is an offence under s. 6 of the regulation with its own set fine. Owners should not file it themselves: an owner-named filing is evidence pointing the wrong way.

Most notices go through the Ministry's online Notice of Project service. The form asks for the constructor's legal name, business number and WSIB details; the project address or location, with GPS coordinates; the type of construction and a description; start and end dates; the expected number of workers regularly on site; the project supervisor's name; and the estimated labour and materials cost, which does not print on the copy. It also asks for the owner's name and address, whether the constructor received a designated substances list from the owner, and which designated substances may be used, handled or disturbed.

That last pair of questions links lesson 6 to this one. If the owner's s. 30 list never reached the constructor, the Notice of Project is where the gap shows.

A signed copy must be posted in a conspicuous place at the project or be available there for an inspector. If the end date moves, the Ministry's guidance asks the constructor to tell the nearest Ministry office so the record stays current.

The rest of the day-one safety file

The notice is one item in a short set of start-up obligations. The owner does not do these, but should know they exist and ask to see them:

  • Registration (Form 1000). Under s. 5 of the regulation, every constructor and every employer engaged in construction completes a registration form before starting work at the project. It is not sent to the Ministry; it stays at the project while that employer is working there.
  • Trench notice. Section 7 adds a separate duty to notify the Ministry about trench work. Ask how the constructor has handled it for site services.
  • Supervisor. Section 14(1) requires the constructor to appoint a supervisor for a project with five or more workers at the same time, and s. 14(2) requires that the work be supervised at all times.
  • Emergency procedures. Section 17 requires written emergency procedures, posted at the project.
  • Facilities. Section 29 of the regulation requires toilet and clean-up facilities, and access to them.
  • Worker representation. Under OHSA s. 8(1), a health and safety representative is needed where more than five workers are regularly employed and no committee is required. Under s. 9, a joint health and safety committee (JHSC) is required on a project with 20 or more workers regularly employed that is expected to last three months or more. The committee needs at least two members below 50 workers and at least four at 50 or more.
Northgate forecast workers on site by month, with OHSA thresholds Bar chart of Halvorsen's forecast of workers regularly on site from March 2027 to March 2028. The count is above 20 from April 2027 to January 2028 and peaks at 62 in October 2027; it is 50 or more from September to November 2027. Dashed lines mark 20 workers, where a joint health and safety committee is required on a project lasting three months or more, and 50 workers, where the committee needs at least four members. 0 10 20 30 40 50 60 70 20: JHSCrequired 50: four ormore members 12 Mar 22 Apr 34 May 46 Jun 40 Jul 48 Aug 55 Sep 62 Oct 58 Nov 44 Dec 30 Jan 18 Feb 10 Mar 2027 2028 Workers
Figure 2. Halvorsen's forecast of workers regularly on site at Northgate (fictional), against the OHSA committee thresholds. The project crosses 20 workers in April 2027 and stays above it for ten months. Source: BRC, based on OHSA ss. 8 and 9 as summarized in Ontario's guide for committees and representatives; worker numbers are illustrative.
View the data
MonthForecast workersRepresentation needed
Mar 202712Health and safety representative
Apr 202722JHSC (at least 2 members)
May 202734JHSC (at least 2 members)
Jun 202746JHSC (at least 2 members)
Jul 202740JHSC (at least 2 members)
Aug 202748JHSC (at least 2 members)
Sep 202755JHSC (at least 4 members)
Oct 202762JHSC (at least 4 members)
Nov 202758JHSC (at least 4 members)
Dec 202744JHSC (at least 2 members)
Jan 202830JHSC (at least 2 members)
Feb 202818JHSC continues while the project lasts
Mar 202810JHSC continues while the project lasts

Safety oversight without becoming the constructor

Lesson 6 showed the tension. The owner wants to know the site is safe, and after R. v. Greater Sudbury (City) any owner with its own staff on site is an employer there and may need a due diligence defence. But an owner who starts directing the work risks taking on the constructor role. The answer is a routine that watches, records and raises, and stops short of instructing.

In practice that routine has four parts. Before award, check the bidders' safety records and programs and keep the review. During the work, receive a monthly safety report from the constructor with the progress report, and read it. Attend site meetings and walk the site with the constructor's superintendent, not alone with trades. When you see a hazard, raise it with the constructor in writing the same day and track the response. Serious events, such as a critical injury or a Ministry order, should reach the owner quickly; the constructor's statutory reporting to the Ministry under OHSA ss. 51 to 53 does not tell the owner anything, so the contract has to.

The owner's safety oversight ladder Six steps from lower to higher owner control. Steps one to four are owner oversight: prequalify the constructor's safety record and program before award; receive and read monthly safety reports and incident notices; attend site meetings and walk the site with the superintendent; raise hazards in writing to the constructor and track the response. A line marks the constructor's territory. Steps five and six, which owners should avoid, are instructing trades or workers how to do the work, and bringing owner forces or a second contractor on site outside the constructor's control. LOWER OWNER CONTROL 1 Prequalify: check the safety record and program before award, and keep the review 2 Receive and read monthly safety reports and incident notices 3 Attend site meetings; walk the site with the constructor's superintendent 4 Raise hazards you see to the constructor in writing, and track the response Constructor's territory: avoid 5 Instruct trades or workers how to do the work 6 Bring owner forces or a second contractor on site outside the constructor's control HIGHER OWNER CONTROL
Figure 3. The owner's safety oversight ladder. Steps 1 to 4 build a due diligence record; steps 5 and 6 can shift the constructor role to the owner. Source: BRC, based on the Ontario constructor guideline and R. v. Greater Sudbury (City).

Contract remedies sit between the two zones. An owner may have rights to require removal of a person, or to suspend work, and the Sudbury court noted the City had not used such rights. Using them when warranted is legitimate, but do it through the contract and the constructor, with legal advice, rather than by instructing people on site.

Northgate worked example

Halvorsen Builders Ltd. (fictional) is the constructor for the Northgate Distribution Centre (fictional) in Vaughan, as the owner's Supplementary Conditions and lesson 6 set out. The trigger check in Figure 1 takes a minute: a $34,950,000 Contract Price and a building with 9.75 m clear height each require a Notice of Project on their own. Mobilization is Monday, March 1, 2027, and the kickoff in lesson 3 set a target to file by Friday, February 19, 2027.

The owner's representative tracks the start-up safety file as part of the mobilization checklist from lesson 5:

ItemWhoBasisNorthgate target
Designated substances list in constructor's handsOwnerOHSA s. 30(3)Done: in tender, before Jan 11, 2027
Notice of Project filed; signed copy postedHalvorsenO. Reg. 213/91 s. 6By Fri Feb 19, 2027
Form 1000 for Halvorsen and each employerEach constructor and employers. 5Before each starts work
Supervisor appointedHalvorsens. 14(1)Before Mon Mar 1, 2027
Written emergency procedures postedHalvorsens. 17Before Mon Mar 1, 2027
Toilet and clean-up facilitiesHalvorsens. 29From Mon Mar 1, 2027
Health and safety representativeWorkers select; Halvorsen ensuresOHSA s. 8(1)March 2027
JHSC establishedHalvorsenOHSA s. 9By April 2027 (20+ workers)

When Halvorsen sends its draft notice, the owner's representative checks three things before mobilization: the owner's legal name and address are right, the form says a designated substances list was received from the owner, and the end date matches the contract. Halvorsen's forecast in Figure 2 peaks at 62 workers in October 2027, so the owner's representative asks at the February site meeting how Halvorsen will grow the committee to four members before September.

The Supplementary Conditions require a monthly safety report with each progress report, covering hours worked, incidents, Ministry visits and orders, and committee minutes. They also require notice to the owner's representative within 24 hours of any critical injury, work refusal or Ministry order. Racking adds one more step: before Monday, January 17, 2028, the racking installer completes its own Form 1000 and Halvorsen's orientation, and Halvorsen tells the Ministry office if its end date has moved.

Owner's move

Demand a copy of the filed Notice of Project before mobilization, plus monthly safety reporting and 24-hour notice of serious events in the Supplementary Conditions.

Check the notice against the contract: owner details, constructor, dates, and the designated substances answer. Check that Form 1000s, the supervisor appointment and emergency procedures exist before day one.

Reject owner-filed notices, owner staff instructing trades, and any start date that arrives before the notice is filed.

Owner's rule: the Notice of Project is the constructor's filing and the owner's evidence. Get a copy, check it, and file it with your safety oversight record.

Common mistakes

  1. Treating the notice as paperwork. It names the constructor in a public filing. If it names the wrong party, fix it before work starts.
  2. Not checking the designated substances answer. A "no list received" answer points to a gap in the owner's s. 30 duty.
  3. Forgetting the end date. When the project runs longer, or a post-takeover contractor extends site work, the record should be updated.
  4. Owner site walks without the constructor. They create pressure to instruct trades directly and weaken the owner's position.
  5. No owner reporting clause. Statutory reports go to the Ministry, not the owner.

Quick quiz

  1. Under O. Reg. 213/91 s. 6, which single fact is enough to require a Notice of Project for a new warehouse?

    1. More than 10 workers on site
    2. Labour and materials expected to cost over $50,000
    3. A building permit was issued
    4. The owner hired a consultant
  2. Who must file the Notice of Project?

    1. The owner
    2. The architect
    3. The constructor
    4. The municipality
  3. What happens to a completed Form 1000 registration?

    1. It is filed online with the Notice of Project
    2. It is kept at the project while that employer works there
    3. It is sent to WSIB
    4. It is attached to the building permit
  4. A project will last 13 months with 20 or more workers regularly employed for most of it. What does OHSA s. 9 require?

    1. Only a health and safety representative
    2. A joint health and safety committee
    3. Nothing, because a constructor is named
    4. A second Notice of Project
  5. The owner's PM sees a worker at an unguarded floor opening. What is the best owner response?

    1. Tell the worker how to rig a guardrail
    2. Ignore it, since safety is the constructor's job
    3. Raise it with the constructor's superintendent at once, confirm in writing and track the response
    4. Stop all work on site personally
Show answers and explanations
  1. B. The cost trigger alone is enough. Northgate also meets the height trigger.
  2. C. OHSA s. 23(2) and s. 6 of the regulation put the duty on the constructor.
  3. B. Form 1000 is not sent to the Ministry; it stays at the project while the employer works there.
  4. B. A JHSC is required on a project with 20 or more workers regularly employed and expected to last three months or more.
  5. C. Raising hazards through the constructor builds the owner's due diligence record without directing the work.

Key terms

Notice of Project
The constructor's notice to the Ministry, before work begins, of a project that meets a trigger in s. 6 of O. Reg. 213/91. A signed copy is posted or kept at the project.
Form 1000
The registration form each constructor and employer completes before starting work at a project, kept on site.
Joint health and safety committee (JHSC)
A committee of worker and management members required on projects with 20 or more workers regularly employed and lasting three months or more.
Health and safety representative
A worker selected to represent workers on health and safety where more than five are regularly employed and no committee is required.
Safety oversight record
The owner's file showing how it chose the constructor, monitored safety and raised hazards.

References

  1. Government of Ontario, O. Reg. 213/91: Construction Projects, ss. 5, 6, 7, 14, 17, 29 (e-Laws).
  2. Government of Ontario, File a work notice (updated April 1, 2026).
  3. Ministry of Labour, Notice of Project requirements and Notice of Project help guide.
  4. Ontario Court of Justice, Set fines, Schedule 67.1 (O. Reg. 213/91).
  5. Government of Ontario, Guide for health and safety committees and representatives (updated August 17, 2026).
  6. Government of Ontario, Constructor guideline (updated August 13, 2026).
  7. Government of Ontario, Occupational Health and Safety Act, R.S.O. 1990, c. O.1, ss. 8, 9, 23, 51 to 53 (e-Laws).
  8. OHS Insider, Ontario eases construction Notice of Project filing rules (proposed changes).

Verified on November 4, 2026.

Next lesson in this trackQuality plans and ITPs

This lesson is general education, not legal advice. Get advice from a construction lawyer on your contract.

PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. Oracle and Primavera are trademarks of Oracle. Microsoft Project is a trademark of Microsoft. BRC Academy is not affiliated with or endorsed by these organizations.