As-planned vs as-built analysis

The simplest way to look at delay is to put the plan next to what actually happened. As-planned vs as-built analysis does exactly that. It is quick, easy to explain and a good first look at any claim. It is also weak on causation, because it shows where the project slipped without showing why. This lesson shows how to do it well and where it stops.

Learning outcomes

  • Perform an as-planned vs as-built comparison at milestone and activity level.
  • Identify where delay accumulated on a project.
  • Explain why the method is weak on causation and concurrency.
  • Use it as a screening step before a fuller analysis.

The lesson

How it works

Take the accepted baseline and the as-built record. Compare start and finish dates for each milestone, then for the activities on the paths that drove completion. The difference shows where delay appeared and how it grew. In AACE RP 29R-03 terms this is observational, static logic: MIP 3.1 when done for the whole project at once, MIP 3.2 when done period by period [1].

As-planned vs as-built, Northgate milestonesPlanned and actual dates for M4 to M9. M4 foundations on time. M5 panels 8 days late. M6 roof 23 days late. M7 power 37 days late. M8 commissioning 55 days late. M9 Ready-for-Takeover 60 days late.Mar 2027JunSepDecMar 2028M4 slab, plannedM4 actualon timeM6 roof, plannedM6 actual+23 daysM9 RFT, plannedM9 actual+60 daysActual duration to milestone
Figure 1. Planned and actual milestones. The bars show where delay accumulated, not why. Days are calendar days from March 1, 2027. Illustrative. Source: BRC, Northgate case study.
View the data
MilestonePlannedActualVariance
M4 Foundations and slabMay 14, 2027May 14, 20270
M5 Panels erectedJun 25, 2027Jul 3, 2027+8
M6 Roof weathertightSep 3, 2027Sep 26, 2027+23
M7 Permanent powerOct 1, 2027Nov 7, 2027+37
M8 Commissioning startsNov 1, 2027Dec 26, 2027+55
M9 Ready-for-TakeoverJan 14, 2028Mar 14, 2028+60

Strengths

It needs only two schedules, it is cheap, and a project director or adjudicator can understand it in minutes. On a small claim, or as the first step on a large one, it often shows quickly whether the claim is plausible and where to look harder.

Limits

The method assumes the baseline logic held all project long, which is rarely true. It does not identify the critical path at the time of each event, so it cannot separate owner delay from contractor delay running in parallel. It shows that the roof was late, not who made it late. On a contested claim it is a starting point, not proof.

Rule of thumb: use as-planned vs as-built to decide where to look, then use a dynamic or modelled method to prove why.

Northgate worked example

Northgate Distribution Centre (fictional) is a 12,000 m² tilt-up warehouse in Vaughan, Ontario, built by Halvorsen Builders Ltd. (fictional) under CCDC 2-2020, with Ridgeline Architects Inc. (fictional) as Consultant. See the Northgate fact sheet. This course follows one delay claim from first notice to settlement. Ready-for-Takeover (M9) was due Friday, January 14, 2028 and was reached on Tuesday, March 14, 2028: 60 calendar days late. All events, dates and amounts are illustrative.

The owner's representative starts her review of Claim C-01 with a milestone comparison (Figure 2). It shows the delay building in two places: 8 days at tilt-up panels (M5), growing to 23 days at roof complete (M6), 37 days at permanent power (M7), 55 days at commissioning start (M8) and 60 days at Ready-for-Takeover (M9).

Northgate milestone varianceM4: 0 days. M5: 8. M6: 23. M7: 37. M8: 55. M9: 60.M4 Foundations and slab0 daysM5 Panels erected8 daysM6 Roof weathertight23 daysM7 Permanent power37 daysM8 Commissioning starts55 daysM9 Ready-for-Takeover60 days
Figure 2. Delay in calendar days at each milestone. Illustrative. Source: BRC, Northgate case study.
View the data
ItemValue
M4 Foundations and slab0 days
M5 Panels erected8 days
M6 Roof weathertight23 days
M7 Permanent power37 days
M8 Commissioning starts55 days
M9 Ready-for-Takeover60 days

The comparison tells her where to look: the summer roof and mezzanine period, the fall power connection, and the winter commissioning. It cannot tell her that 8 of the early days were Halvorsen's crane breakdown, or that the roof deck delay overlapped the mezzanine redesign. Those answers need the windows analysis in lesson 10.

Your move

If you are the owner

  • Run it first. A milestone comparison shows where the delay sits in an hour.
  • Don't accept it as proof of causation. Ask what else happened in each period.
  • Use it to scope the review. Focus effort on the periods where delay grew.
  • Keep milestone dates in every update. It makes this comparison trivial.

If you are the contractor

  • Use it to explain, not to prove. Pair it with causation evidence.
  • Show your own delays too. An honest comparison earns credibility.
  • Check the baseline logic first. If the plan was unrealistic, the comparison misleads.
  • Don't stop here on a large claim. Reviewers will go further.

Common mistakes

  1. Presenting the variance as owner delay. Variance is not causation.
  2. Comparing against an unaccepted baseline. The reference must be agreed.
  3. Ignoring logic changes. Re-sequencing during the job changes the critical path.
  4. Activity-level noise. Focus on driving paths, not every bar.
  5. Skipping it. It is the fastest sanity check available.

Quick quiz

  1. Which AACE MIP is as-planned vs as-built for the whole project at once?

    1. 3.1
    2. 3.3
    3. 3.6
    4. 3.8
  2. What is the main weakness of as-planned vs as-built?

    1. It is expensive
    2. It does not show why delay happened or separate concurrent causes
    3. It needs many updates
    4. It cannot show milestone dates
  3. When is it most useful?

    1. As final proof in arbitration
    2. As a first look to decide where to analyse further
    3. Never
    4. Only for owners
  4. At Northgate, how much delay had built up by roof complete (M6)?

    1. 8 days
    2. 23 days
    3. 37 days
    4. 60 days
  5. What assumption does the method make about logic?

    1. Logic changed every month
    2. The baseline logic held throughout
    3. There was no logic
    4. Logic is irrelevant
Show answers and explanations
  1. A. MIP 3.1 is observational, static, gross.
  2. B. It shows where, not why.
  3. B. It screens and scopes the review.
  4. B. M6 was 23 days late: 8 from the crane plus 15 from the roof deck and mezzanine period.
  5. B. That assumption is often wrong, which limits the method.

Key terms

As-planned schedule
The accepted baseline: the plan before work started.
As-built schedule
The record of actual start and finish dates.
Milestone variance
The difference between planned and actual milestone dates.
Static logic
Analysis that uses one fixed set of schedule logic for the whole project.
Driving path
The chain of activities that controls a milestone date.

References

  1. AACE International, Recommended Practice No. 29R-03, Forensic Schedule Analysis, table of contents and method taxonomy (revision April 25, 2011).
  2. Fenwick Elliott, The SCL Delay and Disruption Protocol: a second edition (November 2017), summarizing the Society of Construction Law Protocol, 2nd edition (February 2017).
  3. Miller Thomson LLP, Ontario Court underlines the evidence and analysis required to establish critical path delays (July 2021).
  4. BRC, Northgate fact sheet (fictional case study, v1, November 4, 2026).

Verified on November 9, 2026.

Next lesson in this trackImpacted as-planned

This lesson is general education, not legal advice. Get advice from a construction lawyer on your contract.

Northgate Distribution Centre, Northgate Logistics Inc., Halvorsen Builders Ltd. and Ridgeline Architects Inc. are fictional and are used for teaching only. AACE is a registered mark of AACE International. BRC Academy is not affiliated with or endorsed by these organizations.