Medical Clinic Construction Cost in Toronto (2026): $460–$800 per Sq Ft

A stethoscope resting on a clipboard

Medical clinic construction in Toronto costs $460 to $800 per square foot in 2026, according to Altus Group’s Canadian Cost Guide range for a new medical clinic or treatment centre in the Greater Toronto Area. That is hard construction cost only: GST/HST, site development, parking, land and financing come on top, so a realistic clinic budget starts from that range and builds up.

Below: how the clinic range compares with offices and hospitals, worked budgets by size, what makes clinics cost more, Toronto permit timing, and what this means for a clinic fit-out in Yorkville or other leased space. The full benchmark is on our medical clinic cost benchmark page.

Medical clinic construction cost in Toronto: the 2026 range

Altus puts a new GTA clinic at about 1.5 to 1.8 times the cost of a Class A office building at each end of the range, and a little under half the cost of a hospital. The gap with offices comes from the building services and room-by-room detail that clinical space needs.

Medical clinic construction cost per sq ft compared with other GTA building types, 2026 Altus Group 2026 hard construction cost ranges for the Greater Toronto Area, in dollars per square foot: Class A office fit-out 160 to 265; Class A office building 305 to 450; medical clinic or treatment centre 460 to 800; hospital 1,030 to 1,620. Clinics sit between offices and hospitals Hard construction cost, $ per sq ft, Greater Toronto Area, 2026 $0 $500 $1,000 $1,500 Class A office fit-out (interior fit-out only) Class A office fit-out: $160 to $265 per sq ft $160–$265 Class A office building (new building) Class A office building: $305 to $450 per sq ft $305–$450 Medical clinic / treatment centre (new building) Medical clinic / treatment centre: $460 to $800 per sq ft $460–$800 Hospital (new building) Hospital: $1,030 to $1,620 per sq ft $1,030–$1,620
Source: Altus Group, 2026 Canadian Cost Guide, GTA ranges as shown on our cost benchmark pages. Hard costs only; excludes GST/HST, land, financing and soft costs.
View the data
Building typeLow ($/sq ft)High ($/sq ft)
Class A office fit-out (interior fit-out only)$160$265
Class A office building (new building)$305$450
Medical clinic / treatment centre (new building)$460$800
Hospital (new building)$1,030$1,620

Turning the range into a first clinic budget is simple arithmetic on the floor area:

Hard-cost budget for a new clinic building at $460–$800 per sq ft
Gross floor areaLowHigh
5,000 sq ft$2.3M$4.0M
10,000 sq ft$4.6M$8.0M
30,000 sq ft$13.8M$24.0M
Simple arithmetic on the Altus Group 2026 GTA range (the 30,000 sq ft row is the worked example on our medical clinic benchmark page). Hard cost only: add GST/HST, site development, parking, land, financing, design fees, equipment and contingency.

Treat the low end as a simple, mostly consult-and-exam clinic and the high end as a clinic with procedure rooms, imaging or more demanding mechanical systems. Where your project lands depends on the clinical program, not the square footage alone.

What makes a clinic budget higher than an office

  1. Plumbing. Hand sinks in exam and treatment rooms, accessible washrooms and, for some clinics, sterilization or lab areas mean far more fixtures, drains and water lines per square foot than an office.
  2. Mechanical and ventilation. CSA Z317.2:24, the Canadian standard for HVAC in health care facilities, sets requirements that are more stringent than those for non-health care buildings. Check with your design team which parts apply to your clinic type early, because ventilation drives ductwork, equipment size and ceiling space.
  3. Imaging and shielding. X-ray rooms need shielding built into walls, floors or doors. In Ontario, X-ray equipment used on people is registered through the Ministry of Health’s X-Ray Inspection Service, and the application includes plan drawings showing shielding. Build that review into the schedule before walls close.
  4. Accessibility. Patients arrive with mobility devices, so entrances, corridors, washrooms and exam rooms need space and hardware to suit. Retrofitting an older building for barrier-free access can add cost a new building avoids.
  5. Infection control and finishes. Cleanable, seamless finishes, more doors and more millwork cost more than standard office finishes, and work inside an occupied medical building needs extra protection and sequencing.
Wall-mounted diagnostic instruments above a counter in an exam room
Every exam room needs services an office doesn’t: power and backing for wall-mounted equipment, a hand sink and easy-to-clean finishes. Photographed in Los Angeles. Photo: Brian Wangenheim on Unsplash (Unsplash Licence).

Clinic fit-out in Yorkville and other leased space

Many Toronto clinics, including in Yorkville, go into existing buildings rather than new ones. The Altus clinic range is for a new building, and Altus doesn’t publish a separate clinic fit-out range, so we don’t offer one here. Office fit-out ranges (Class A $160 to $265 per sq ft in the GTA) aren’t a substitute: they don’t carry clinical plumbing, ventilation or shielding. See our office fit-out cost guide for what those ranges include.

For a leased clinic, the base building decides much of the cost. Before you sign, confirm where plumbing stacks and risers are, whether the floor and HVAC can take clinical loads, what the landlord delivers, and whether the use is permitted under zoning.

Toronto permit timing for a clinic

The City of Toronto sets review targets by permit stream. They apply only to complete applications:

City of Toronto building permit review time frames City of Toronto target time frames for review of a complete building permit application, in business days: Express Service 3; House 10; Small Building (Part 9) 15; Large Building (Part 3) 20; Complex Building 30. Toronto permit review targets Business days for review of a complete application, by review stream 0 10 20 30 Express Service Express Service: 3 business days 3 days House House: 10 business days 10 days Small Building (Part 9) Small Building (Part 9): 15 business days 15 days Large Building (Part 3) Large Building (Part 3): 20 business days 20 days Complex Building Complex Building: 30 business days 30 days
Source: City of Toronto, Building Permit Review Streams. These are review targets, not approval dates; the clock doesn’t run on incomplete applications.
View the data
Review streamBusiness days
Express Service3
House10
Small Building (Part 9)15
Large Building (Part 3)20
Complex Building30

The City is direct about the catch: “There is no time frame for review of incomplete permit applications,” and applications without a Zoning Applicable Law Certificate “are considered incomplete.” Start zoning early, especially for a change of use in an existing building. Our Toronto building permit timeline guide walks through the full sequence.

How to build a clinic budget you can trust

  1. Start from the clinical program: room types, counts, imaging and procedures.
  2. Price hard cost from the benchmark, then add taxes, design fees, permits, equipment, IT, furniture and contingency.
  3. Test the base building or site before you commit to a lease or purchase.
  4. Refine the estimate at each design stage. Our Class D estimate guide explains how wide early ranges really are, and our owner tools help you size them.

Run your own numbers: our clinic cost calculator turns the range into a budget for your floor area, with soft costs and contingency.

FAQ

How much does medical clinic construction cost in Toronto?

Altus Group's 2026 Canadian Cost Guide puts the hard construction cost of a new medical clinic or treatment centre in the Greater Toronto Area at $460 to $800 per square foot. That excludes GST/HST, site development, parking, land and financing.

How much should I budget for a 10,000 sq ft medical clinic?

At $460 to $800 per square foot, the hard cost of a new 10,000 sq ft clinic building in the GTA works out to about $4.6 million to $8.0 million, before taxes, land, financing, design fees, equipment and contingency.

Does the same cost apply to a clinic fit-out in Yorkville or another leased space?

Not directly. The Altus range is for a new clinic building. Altus does not publish a separate range for fitting out a clinic in leased space, so a fit-out budget should be built from the actual space, the services it needs and the landlord's base building, then checked by a cost consultant.

How long does a Toronto building permit take for a clinic?

The City of Toronto's review targets for a complete application range from 3 business days for Express Service to 15 for a Small Building (Part 9), 20 for a Large Building (Part 3) and 30 for a Complex Building. The City says there is no time frame for reviewing incomplete applications, and an application without a Zoning Applicable Law Certificate is considered incomplete.

The bottom line

At $460 to $800 per square foot in hard cost alone, a new Toronto clinic is a specialized building, and the clinic budget should be built that way: from the program, the services and the site, not from an office number. Planning a clinic or a clinic fit-out? Book a 30-minute call and we’ll help you test the budget before you commit.

Sources: Altus Group, 2026 Canadian Cost Guide, GTA medical clinic / treatment centre range, as shown on our medical clinic benchmark page; City of Toronto, Building Permit Review Streams; Standards Council of Canada, CSA Z317.2:24 HVAC in health care facilities; Ontario, Guidance on completing the X-ray registration and application form. Cover photo: Sasun Bughdaryan on Unsplash (Unsplash Licence). This article is general information, not professional advice for a specific project.