Resources / Cost benchmarks / Hospital Construction
GTA construction cost · 2026

Hospital construction cost per sq ft in Toronto

General and acute care hospitals in the Greater Toronto Area, hard cost only.

2026 GTA range$1,030–$1,620per sq ft, hard cost

Short answer (November 2026): Hospital construction in the GTA costs $1,030–$1,620 per sq ft in hard costs, before soft costs, contingency and HST (Altus Group 2026 Canadian Cost Guide). For example, a general or acute care hospital of 500,000 sq ft comes to $515.0M – $810.0M in hard cost.

Worked example

A general or acute care hospital of 500,000 sq ft

Hard cost (500,000 × $1,030–$1,620)$515.0M – $810.0M
Soft costs at 20%$103.0M – $162.0M
Contingency at 10%$61.8M – $97.2M
Indicative total$679.8M – $1.07B

Included: the building above grade, including foundations.
Not included: GST/HST, site development, parking, land and financing. Soft costs and contingency above are illustrative assumptions; change them in the calculator.

Source: Altus Group, 2026 Canadian Cost Guide (GTA hard costs, CAD per sq ft), used with permission. Ranges are indicative; your site, scope and procurement route will move the number. See all 17 building types →

Why hospitals cost this much, and what two Ontario projects show: our hospital cost guide.