Total float and free float

Float is the room an activity has to move. Oracle Primavera P6 calculates two kinds every time you schedule: total float, measured against the project's finish, and free float, measured against the very next activities. They answer different questions. Total float tells an owner how close an activity is to delaying completion; free float tells the contractor how much an activity can slip before it disturbs the trade that follows. Read them together and a schedule starts to show where its real slack is, and where it has none.

Learning outcomes

  • Define total float and free float as P6 calculates them, and explain why an activity can have one without the other.
  • Calculate both by hand from early and late dates for a small network.
  • Find the P6 settings that change float: Compute Total Float as, the project Must Finish By date and the float end date.
  • Explain negative float, and use float values to target an owner's schedule review.

The lesson

Two definitions

Oracle defines total float as the time an activity can be delayed without delaying the project's finish date, and free float as the time it can be delayed without delaying the activities that immediately follow it [1]. P6 recalculates both every time you schedule, and you cannot type over them [1]. To see them, choose Project, Activities, select an activity, and open the Status tab of Activity Details, or add the Total Float and Free Float columns to the Activity Table [1].

Free float can never be larger than total float. If an activity can slip three days before it touches its successor, and the successor itself has no room, those three days are all the room the activity has. The reverse is common: an activity can have total float and zero free float, because its float is shared with the activities after it on the same chain.

How P6 calculates total float

The forward pass gives each activity an early start and early finish; the backward pass gives a late start and late finish (Lesson 10). Total float is the gap between them, counted in working time on the activity's calendar. The Compute Total Float as setting on the General tab of Schedule Options decides which gap [2]:

  • Start Float = Late Start − Early Start.
  • Finish Float = Late Finish − Early Finish.
  • Smallest of Start Float and Finish Float, which Oracle calls the most critical value.

For a not-started activity on a single calendar the three give the same answer. They can differ when an activity is in progress or when calendars differ along a chain, which is why the owner records the setting with every baseline.

What sets the end of float

Total float needs an end date to measure against. If the project has a Must Finish By date on the Dates tab of Project Details, which Oracle describes as a date constraint on the project end, the backward pass starts from it [3]. If not, it starts from the latest early finish in the network [4]. A Must Finish By date later than the calculated finish gives every activity extra float; one earlier than the calculated finish gives the critical chain negative float. With several projects open, Calculate float based on end date of chooses between each project's own finish and the latest finish of all opened projects; the second option gives open-ended activities more float [2].

Negative float

Negative total float means the activity is already behind a date it has to meet. It comes from a constraint or a Must Finish By date that the logic cannot achieve. It is not an error; it is the schedule telling you, in working days, how far the plan is from the target. P6's Check Schedule report counts activities with negative float, and also flags large float above a threshold you set, because large float usually means missing logic [5].

Free float and driving logic

Free float links directly to the driving relationships in Lesson 9. P6 EPPM Help states that P6 treats a relationship as driving when free float is zero or less, the activity has no Start On or Finish On constraint, and it has no actual finish [6]. A predecessor with a day or two of free float is not driving today but is the first thing to check when its successor starts to slip.

Screenshot to come
Screenshot to come: P6 Professional v26, project NDC-BL00 (EPS NDC.SUB), Project, Activities, activity A3300 Dock and leveller pits selected, Activity Details Status tab showing Total Float 3d and Free Float 0d

Northgate worked example

Northgate Distribution Centre (fictional) is a 12,000 m² tilt-up warehouse in Vaughan, Ontario, with 14 dock doors and 2 drive-in doors, built by Halvorsen Builders Ltd. (fictional) for Northgate Logistics Inc. (fictional) (see the Northgate fact sheet). The extract below is from WBS 3, foundations and slab-on-grade, in Halvorsen's baseline NDC-BL00. Dates are Halvorsen's illustrative baseline dates on the Monday-to-Friday, 8-hour calendar, with Good Friday (Fri Mar 26, 2027) as a holiday. In this extract the footings and the slab are on the longest path, so their total float is zero.

  • A3100 Footings and piers, 19d, Mon Mar 15 to Fri Apr 9.
  • A3200 Underslab services, 10d, SS 7d from A3100: Wed Mar 24 to Wed Apr 7. FS to the slab.
  • A3300 Dock and leveller pits, 8d, SS 5d from A3100: Mon Mar 22 to Thu Apr 1. FS to A3310.
  • A3310 Leveller embeds and curb angles, 3d: Fri Apr 2 to Tue Apr 6. FS to the slab.
  • A3500 Slab-on-grade, 25d, from Mon Apr 12, driven by the footings.
Northgate WBS 3: total float and free float on a Gantt chart A Gantt chart from March 15 to April 16, 2027 with Good Friday, March 26, shaded. A3100 Footings and piers, March 15 to April 9, total float 0. A3200 Underslab services, March 24 to April 7, with a light extension to April 9: total float 2 days, free float 2 days. A3300 Dock and leveller pits, March 22 to April 1, with an orange-outlined extension to April 6: total float 3 days, free float 0. A3310 Leveller embeds, April 2 to April 6, with a light extension to April 9: total float 3 days, free float 3 days. A3500 Slab-on-grade starts April 12 and continues to May 14, total float 0. Good Fri Mar 15 Apr 1 Apr 12 A3100 Footings & piers · TF 0 A3200 Underslab · TF 2 · FF 2 A3300 Pits · TF 3 · FF 0 A3310 Embeds · TF 3 · FF 3 A3500 Slab-on-grade · TF 0 continues to May 14 Free float Total float shared with the next activity
Figure 1. Total and free float in Northgate's WBS 3 (illustrative baseline dates). The pits have three days of total float but none of their own: it is shared with the embeds that follow. Source: BRC, based on the Northgate fact sheet and Oracle Primavera P6 Professional Help v26, View activity float values [1].
View the data
ActivityEarly startEarly finishLate startLate finishTFFF
A3100 Footings & piersMar 15Apr 9Mar 15Apr 90d0d
A3200 Underslab servicesMar 24Apr 7Mar 29Apr 92d2d
A3300 Dock & leveller pitsMar 22Apr 1Mar 25Apr 63d0d
A3310 Leveller embedsApr 2Apr 6Apr 7Apr 93d3d
A3500 Slab-on-gradeApr 12May 14Apr 12May 140d0d

Working it out by hand

The slab starts Mon Apr 12, so anything that must finish before it has a late finish of Fri Apr 9. Work backwards (Figure 2):

  • A3310 Embeds: late finish Fri Apr 9; three days back gives a late start of Wed Apr 7. Early start was Fri Apr 2. Total float: Apr 2 to Apr 7 is 3 working days. Its successor, the slab, cannot start before Apr 12 anyway, so free float is also 3 days.
  • A3300 Pits: late finish is the day before the embeds' late start, Tue Apr 6; eight days back gives a late start of Thu Mar 25. Total float is again 3 days. But the embeds start the day after the pits finish, so free float is 0.
  • A3200 Underslab: late finish Fri Apr 9, late start Mon Mar 29 (Good Friday skipped). Early start was Wed Mar 24, so total float and free float are both 2 days.

The lesson in the pits is the important one. A superintendent looking only at total float sees three days on the pits and three on the embeds, and may think there are six. There are three, shared between the two activities. Spend them on the pits and the embeds have none left.

Activity-on-node calculation for the pits, embeds and slab Three activity nodes linked top to bottom by Finish to Start arrows. Each node has early start and early finish in the top row, the activity name in the middle and late start and late finish in the bottom row, with total float and free float beside it. A3300 Pits: ES March 22, EF April 1, LS March 25, LF April 6, TF 3, FF 0. A3310 Embeds: ES April 2, EF April 6, LS April 7, LF April 9, TF 3, FF 3. A3500 Slab: ES April 12, EF May 14, LS April 12, LF May 14, TF 0, FF 0. Formulas: TF equals LS minus ES; FF equals the gap to the earliest successor start. ES Mar 22EF Apr 1 A3300 Pits · 8d LS Mar 25LF Apr 6 TF 3dFF 0d FS ES Apr 2EF Apr 6 A3310 Embeds · 3d LS Apr 7LF Apr 9 TF 3dFF 3d FS ES Apr 12EF May 14 A3500 Slab · 25d LS Apr 12LF May 14 TF 0dFF 0d TF = Late Start − Early Start (working days) FF = working days before the earliest successor start
Figure 2. Early and late dates, total float and free float for three linked activities (illustrative baseline dates, 2027). Source: BRC, based on Oracle Primavera P6 Professional Help v26, General tab of Schedule Options and View activity float values [1][2].

A what-if: when the pits run long

Suppose, as an illustration only, the pits take 12 days instead of 8, finishing Wed Apr 7. The embeds move to Thu Apr 8 to Mon Apr 12, and the slab cannot start until Tue Apr 13, finishing Mon May 17, one working day after M4 (Fri May 14). The pits used their three days of float, and the fourth day went straight to the slab.

What P6 shows next depends on the setup. With no constraint on M4, the slab simply moves and total float on the longest path stays at zero, because float is measured against the new latest finish. If Halvorsen's file carries the M4 contract date as a finish constraint on the milestone, the pits, embeds and slab all show −1d of total float (Figure 3). That negative number is useful: it tells the owner, at a glance, how much recovery the contractor needs to show.

Total float before and after a four-day overrun on the pits Diverging bar chart of total float in working days, with a zero line. Before the overrun: pits 3, embeds 3, slab 0. After a four-day overrun with M4 held by a finish constraint at May 14: pits minus 1, embeds minus 1, slab minus 1. Negative bars are orange and extend left of zero. 0 Before A3300 Pits3d A3310 Embeds3d A3500 Slab0d After +4d on pits, M4 held at May 14 A3300 Pits−1d A3310 Embeds−1d A3500 Slab−1d
Figure 3. Total float before and after an illustrative four-day overrun on the dock pits, with the M4 date held by a finish constraint. Three days of float absorb most of it; the last day becomes negative float on the whole chain. Source: BRC, based on the Northgate fact sheet and Oracle Primavera P6 Professional Help v26, View activity float values and Dates tab, Project Details [1][3].
View the data
ActivityTF beforeTF after +4d on pits
A3300 Dock & leveller pits3d−1d
A3310 Leveller embeds3d−1d
A3500 Slab-on-grade0d−1d
Screenshot to come
Screenshot to come: P6 Professional v26, NDC-BL00 Activities window filtered to WBS 3, columns Activity ID, Activity Name, Original Duration, Early Start, Early Finish, Late Start, Late Finish, Total Float, Free Float, with A3200, A3300 and A3310 showing float bars in the Gantt chart
Screenshot to come
Screenshot to come: P6 Professional v26, NDC-BL00, Tools, Schedule, Options, General tab of Schedule Options with the Compute Total Float as drop-down open showing Start Float, Finish Float and Smallest of Start Float and Finish Float

Owner's move

  • Record the float settings. Compute Total Float as, the Must Finish By date and the float end date setting go in the owner's baseline record. A change at update time can move float without any change on site.
  • Read free float before agreeing a re-sequence. When a contractor proposes to "use float" on an activity, check whether that float is its own (free) or borrowed from the activities after it.
  • Treat large float as a logic question. An activity with months of float is usually missing a successor. Check Schedule's Large Float check finds them [5].
  • Track float on the near-critical paths, not just the critical one. A path that drops from 9 days to 2 over two updates is the next critical path (Lesson 11).
  • Decide who owns float in the contract, not in P6. P6 only calculates float. Whether it belongs to the owner, the contractor or the project is set by the contract and its Supplementary Conditions, and should be settled before the first delay discussion.

Common mistakes

  1. Adding up total float along a chain. Float on consecutive activities is usually shared. Three days on the pits and three on the embeds is three days, not six.
  2. Trusting float in a file with open ends. An activity with no successor takes its float from the project end and looks safer than it is.
  3. Ignoring the Must Finish By date. A Must Finish By date set later than the contract date hands every activity float that does not exist under the contract.
  4. Treating negative float as a software error. It is a measurement of how far the plan is from a date it must meet.
  5. Comparing float across calendars as if it were the same unit. A day of float on a seven-day calendar is not a day on a five-day calendar.

Quick quiz

  1. Free float is the time an activity can slip without delaying:

    1. The project finish date
    2. The activities that immediately follow it
    3. The data date
    4. The baseline
  2. With Compute Total Float as set to Finish Float, total float equals:

    1. Late Start − Early Start
    2. Late Finish − Early Finish
    3. Early Finish − Early Start
    4. Late Finish − Late Start
  3. Northgate's pits show TF 3d and FF 0d; the embeds that follow show TF 3d and FF 3d. How much can the pits slip before the slab moves?

    1. 0 days
    2. 3 days
    3. 6 days
    4. Cannot tell
  4. A project's Must Finish By date is earlier than its calculated finish. The critical chain will show:

    1. Zero float
    2. Positive float
    3. Negative float
    4. No float values
  5. Which statement is true in P6?

    1. You can type a total float value into an activity
    2. Free float can exceed total float
    3. Float is recalculated every time you schedule
    4. Float is counted in calendar days
Show answers and explanations
  1. B. Oracle defines free float against the activities that immediately follow [1].
  2. B. Finish Float is Late Finish minus Early Finish [2].
  3. B. The three days are shared with the embeds; after three days the slab moves.
  4. C. The backward pass starts from a date the logic cannot meet, so the chain shows negative float [3].
  5. C. Float is calculated automatically each time you schedule and cannot be edited directly [1].

Key terms

Total float
The time an activity can be delayed without delaying the project finish date.
Free float
The time an activity can be delayed without delaying the activities that immediately follow it.
Start float / finish float
Late start minus early start, and late finish minus early finish; P6 lets you choose either, or the smaller, as total float.
Negative float
Total float below zero, showing that a constraint or Must Finish By date cannot be met by the current logic.
Must Finish By
A date constraint on the project end, set on the Dates tab of Project Details, that the backward pass starts from.
Shared float
Total float that belongs to a chain of activities, so that using it on one reduces it on the others.

References

  1. Oracle. View activity float values. Primavera P6 Professional Help, Version 26.
  2. Oracle. General tab - Schedule Options dialog box. Primavera P6 Professional Help, Version 26.
  3. Oracle. Dates tab - Project Details. Primavera P6 Professional Help, Version 26.
  4. Oracle. Scheduling projects. Primavera P6 Professional User Guide, Version 26.
  5. Oracle. Dates and Durations tab - Check Schedule dialog box. Primavera P6 Professional Help, Version 26.
  6. Oracle. Working with the Activity Network. Primavera P6 EPPM Help, Version 26.

Verified on November 6, 2026.

Next lesson in this trackConstraints

PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. Oracle and Primavera are trademarks of Oracle. Microsoft Project is a trademark of Microsoft. BRC Academy is not affiliated with or endorsed by these organizations.