Durations and duration types

A duration in Oracle Primavera P6 looks like a simple number of days, but P6 treats it as working time on a calendar, tracks it in four separate fields, and ties it to resource units through an equation. The duration type decides which part of that equation gives way when someone edits the schedule. Get it wrong in a resource-loaded file and a crew size, an hours budget or a finish date changes without anyone meaning to change it. This lesson explains durations and the four duration types, and what an owner should check in a contractor's baseline.

Learning outcomes

  • Explain how P6 stores and displays durations, and the difference between Original, Remaining, Actual and At Completion durations.
  • Use the equation Duration = Units ÷ Units/Time to predict what P6 recalculates when one value changes.
  • Choose and set the four duration types at activity and project level in P6 Professional.
  • Check a contractor's baseline for duration and duration-type problems before reviewing logic.

The lesson

A duration is working time on a calendar

When you type 5d into an activity's duration, P6 does not store "five days". It stores working time and counts it on the activity's calendar, which is why the same five days can finish on a Friday or the following Monday depending on holidays (see Lesson 5 on calendars). Oracle notes that P6 recalculates what you enter using the project calendar and the standard time periods your administrator has set, and that the available abbreviations are listed under Admin, Admin Preferences, on the Time Periods tab when you are connected to a P6 Professional database. On an EPPM database the same settings are in Application Settings [1]. If you want P6 to show the unit after each number, turn on Show Duration Label on the Time Units tab of User Preferences [1].

The practical point for owners: a duration only means something together with its calendar and the hours-per-day setting behind it. On Northgate, Monday to Friday at 8 hours a day, 1d is 8 hours of work.

Four duration fields, one activity

P6 keeps several durations for every activity. You enter them on the Status tab of Activity Details (choose Project, Activities, select the activity, then Status), and which field you can edit depends on whether the activity has started [1]:

  • Original (shown as Planned in some views) is the planned working time from planned start to planned finish [1][2].
  • Actual is working time from the actual start to the actual finish, or to the data date while the activity is in progress [2].
  • Remaining is working time from the remaining start to the remaining finish. Before the activity starts it equals the planned duration, and it is zero once the activity is complete [2].
  • At Complete is working time from the current start to the current finish, so for a started activity it adds the time already spent to the time still to go [2].

Figure 1 shows the four fields on one in-progress activity. The distinction matters at every update. A contractor who changes the Original duration of a started activity to make it "fit" is rewriting the plan, not reporting progress. Remaining duration is the field that should move.

The four P6 duration fields on one in-progress activity A timeline with a vertical data date line. The Original duration bar spans the planned start to the planned finish, 25 days. Below it, the Actual duration bar runs from the actual start to the data date, 10 days, and the Remaining duration bar runs from the data date to the remaining finish, 18 days. The At Complete bar spans both, 28 days, ending three days later than the original finish. Data date Original (planned) 25d Actual 10d done Remaining 18d to go At Complete = Actual + Remaining 28d 3d later than the plan Illustrative values
Figure 1. Original, Actual, Remaining and At Complete durations on one in-progress activity (illustrative). The Original duration is the plan; progress is reported through Actual and Remaining. Source: BRC, based on Oracle Primavera P6 Professional Help v26, Enter activity durations, and P6 EPPM Help v26, Durations columns [1][2].
View the data
FieldValueMeasured from
Original25dPlanned start to planned finish
Actual10dActual start to data date
Remaining18dData date to remaining finish
At Complete28dActual start to remaining finish

The equation behind duration types

Once an activity has resources, P6 keeps three numbers in balance: Duration = Units ÷ Units/Time [3]. Units are the total hours of work (say 800 crew-hours). Units/Time is the rate (say 4 workers, or 32 hours a day). Change one and P6 must change another to keep the equation true. The duration type tells P6 which one to change [3]. Oracle's field description says the type should match the least flexible factor on the activity: the schedule, the work effort or the resource availability [4].

That is why the duration type only matters when resources are assigned. Oracle describes the field as controlling how remaining duration, units and units per time are calculated when you update an activity that has resources [4]. In an unloaded schedule, every type gives the same dates.

The four duration types

Oracle lists four types and says which kind of activity each usually suits [5]:

  • Fixed Units/Time. The rate stays put. Use it where a fixed crew produces at a fixed rate; Oracle links it most often to Resource Dependent activities.
  • Fixed Duration & Units/Time. The duration stays put and the remaining units change. Use it where the work must be done in a fixed period whatever resources are assigned; Oracle links it most often to Task Dependent activities.
  • Fixed Units. Total work stays put, so adding resources shortens the duration; most often used with Resource Dependent activities.
  • Fixed Duration & Units. Duration and total work both stay put, and the rate changes; most often used with Task Dependent activities.

Figure 2 summarizes what P6 recalculates for the three most common edits, based on Oracle's synchronization rules [3].

What P6 recalculates for each duration type Four cards, one per duration type, each with three rows: what P6 recalculates when you change units, when you change duration, and when you change units per time. Fixed Units/Time: units change recalculates duration; duration change recalculates units; units per time change recalculates duration. Fixed Duration and Units/Time: units change recalculates units per time; duration change recalculates units; units per time change recalculates units. Fixed Units: units change recalculates duration; duration change recalculates units per time; units per time change recalculates duration. Fixed Duration and Units: units change recalculates units per time; duration change recalculates units per time; units per time change recalculates units. Values that change the finish date are highlighted in orange. You change → P6 recalculates moves the finish date Fixed Units/Time Units → Duration Duration → Units Units/Time → Duration Fixed Duration & Units/Time Units → Units/Time Duration → Units Units/Time → Units Fixed Units Units → Duration Duration → Units/Time Units/Time → Duration Fixed Duration & Units Units → Units/Time Duration → Units/Time Units/Time → Units
Figure 2. The value P6 recalculates when you edit units, duration or units per time, by duration type. Only Fixed Units/Time and Fixed Units let a change in work or rate move the finish date. Source: BRC, based on Oracle Primavera P6 Professional Help v26, Synchronizing activity duration, units, and resource units/time [3].
View the data
Duration typeChange unitsChange durationChange units/time
Fixed Units/TimeDurationUnitsDuration
Fixed Duration & Units/TimeUnits/timeUnitsUnits
Fixed UnitsDurationUnits/timeDuration
Fixed Duration & UnitsUnits/timeUnits/timeUnits

Setting the duration type

For one activity, choose Project, Activities, select the activity, open Activity Details, click the General tab and pick the Duration Type. The field is greyed out for Start and Finish Milestones, which have no duration [5]. For a whole project, choose Enterprise, Projects, open Project Details, click the Defaults tab and set the duration type under Defaults for New Activities. That default applies only to activities created afterwards; existing activities keep their type [6]. To change many activities at once, add the Duration Type column to the Activity Table and fill it down. In P6 EPPM the same field appears in the activity's General details on the Activities page.

Screenshot to come
Screenshot to come: P6 Professional v26, project NDC-BL00 (EPS NDC.SUB), Project, Activities, activity A3500 Slab-on-grade selected, Activity Details General tab with the Duration Type drop-down open showing all four types; Activity Type shows Task Dependent

Northgate worked example

Northgate Distribution Centre (fictional) is a 12,000 m² tilt-up warehouse in Vaughan, Ontario, built by Halvorsen Builders Ltd. (fictional) for Northgate Logistics Inc. (fictional) under a CCDC 2-2020 stipulated price contract (see the Northgate fact sheet). Halvorsen's baseline is imported as NDC-BL00 into the owner's NDC.SUB branch of the EPS. In Lesson 7 we checked its activity types. Now the owner's scheduler checks durations.

The slab, resource-loaded

Activity A3500, Slab-on-grade (WBS 3.2), is Task Dependent with an Original duration of 25d, from Mon Apr 12 to Fri May 14, 2027, ending at the M4 milestone. For this example, assume Halvorsen has loaded it with a concrete finishing crew of 4 workers, 8 hours a day: 4 × 8 × 25 = 800 hours (illustrative numbers). The activity is in balance: 800 h ÷ 32 h/d = 25d.

Halvorsen's site superintendent wants to show the slab done in 20 days. What happens to the hours and the crew depends on the duration type (Figure 3):

  • Fixed Units/Time or Fixed Duration & Units/Time: P6 keeps the crew at 4 and cuts the hours to 640. The schedule now claims the same slab can be placed and finished with 160 fewer hours of work. Nothing about the scope changed.
  • Fixed Units or Fixed Duration & Units: P6 keeps the 800 hours and raises the rate to 40 h/d, which is 5 workers. That is at least a statement Halvorsen can be asked to stand behind: a bigger crew.
Cutting the slab from 25 to 20 days under each duration type Horizontal bar chart of total crew-hours on the Northgate slab after the duration is cut from 25 to 20 days. Before the change: 800 hours at 4 workers. Fixed Units/Time: 640 hours, 4 workers. Fixed Duration and Units/Time: 640 hours, 4 workers. Fixed Units: 800 hours, 5 workers. Fixed Duration and Units: 800 hours, 5 workers. The two 640-hour bars are highlighted in orange because work disappeared from the schedule. Before: 25d 800 h · 4 workers After the duration is cut to 20d: Fixed Units/Time 640 h · 4 workers Fixed Duration & Units/Time 640 h · 4 workers Fixed Units 800 h · 5 workers Fixed Duration & Units 800 h · 5 workers
Figure 3. Total crew-hours on Northgate's slab after its duration is cut from 25 to 20 days (illustrative resource loading). Orange bars lost work without any change in scope. Source: BRC, based on the Northgate fact sheet and Oracle Primavera P6 Professional Help v26, Synchronizing activity duration, units, and resource units/time [3].
View the data
CaseDurationUnits (h)Units/timeCrew
Before25d80032 h/d4
Fixed Units/Time20d64032 h/d4
Fixed Duration & Units/Time20d64032 h/d4
Fixed Units20d80040 h/d5
Fixed Duration & Units20d80040 h/d5

The opposite edit

Now suppose a change in slab thickness adds work and the estimator raises the units from 800 to 1,000 hours. Under Fixed Units/Time or Fixed Units, P6 lengthens the duration: 1,000 ÷ 32 = 31.25 days, so the slab and everything driven by it moves out, including M4. Under either of the two Fixed Duration types, the duration stays at 25d and the crew rate goes up instead [3]. Neither is wrong. What the owner needs to know is which one the contractor chose, so that a cost change and a time change are not quietly traded for each other.

The review

The owner's scheduler adds the columns Duration Type, Original Duration, Remaining Duration and At Completion Duration to the Activities window, groups by Duration Type, and checks:

  • One deliberate default. Most construction tasks in one type, recorded from the Project Details Defaults tab.
  • Exceptions with reasons. Any Fixed Units or Fixed Units/Time activity should be resource-loaded and Resource Dependent or otherwise explained.
  • Durations within the specification. The Northgate schedule specification asks that construction activities not exceed 20 working days unless the owner accepts a reason. A slab at 25d is an obvious candidate for splitting into pours. P6's Check Schedule report includes a Large Durations check for exactly this [7].
  • Original equals At Completion at baseline. In a baseline with no progress, the two should match. If they don't, something has already been statused.
Screenshot to come
Screenshot to come: P6 Professional v26, Enterprise, Projects, NDC-BL00 selected, Project Details Defaults tab showing Duration Type, Percent Complete Type, Activity Type and Calendar under Defaults for New Activities
Screenshot to come
Screenshot to come: P6 Professional v26, NDC-BL00 Activities window grouped by Duration Type (View, Group and Sort By), columns Activity ID, Activity Name, Duration Type, Original Duration, Remaining Duration, At Completion Duration, with WBS 3 activities A3100 to A3500 visible

Owner's move

  • Name the default duration type in the specification. For an unloaded or lightly loaded schedule, a Fixed Duration type keeps dates stable when hours are edited. Whatever you choose, ask for it in writing and check the Defaults tab.
  • Ask for durations in working days. Hours or weeks invite rounding errors and confuse the hours-per-day conversion.
  • Set a maximum duration. Long activities hide progress. A 20-working-day limit for construction work, with exceptions for procurement and Level of Effort, is a common, workable rule.
  • Watch Original durations on started work. In updates, compare Original Duration against the baseline. A change there is a re-plan and needs an explanation, not a progress entry.

Common mistakes

  1. Changing the project default and expecting existing activities to follow. The Defaults tab affects new activities only [6].
  2. Squeezing a duration on Fixed Units/Time. The work hours shrink to fit, and the schedule now understates effort.
  3. Editing Original duration to report progress. Status goes in Actual and Remaining; Original is the plan.
  4. Ignoring the calendar behind "d". A day is whatever the hours-per-period setting says. Mixed 8-hour and 10-hour calendars make day counts misleading.
  5. Mixing duration types for no reason. Two identical pours with different types will react differently to the same edit.

Quick quiz

  1. The equation P6 keeps in balance for a resourced activity is:

    1. Units = Duration ÷ Units/Time
    2. Duration = Units ÷ Units/Time
    3. Duration = Units × Units/Time
    4. Units/Time = Duration × Units
  2. On a Fixed Units/Time activity, you shorten the duration. P6 recalculates:

    1. Units
    2. Units/Time
    3. The calendar
    4. Nothing
  3. You change the project's default duration type on the Defaults tab. Existing activities:

    1. Switch to the new type
    2. Switch only if not started
    3. Keep their current type
    4. Lose their resource assignments
  4. For an activity that has started, the duration that should change when the contractor reports progress is:

    1. Original
    2. Remaining
    3. Planned
    4. Baseline
  5. Northgate's slab has 800 hours of work. Under Fixed Units, the duration is cut from 25d to 20d. The crew rate:

    1. Stays at 32 h/d
    2. Rises to 40 h/d
    3. Falls to 25.6 h/d
    4. Cannot change
Show answers and explanations
  1. B. Oracle states the relationship as Duration = Units ÷ Units/Time [3].
  2. A. Fixed Units/Time holds the rate, so a duration change recalculates units [3].
  3. C. The default applies only to new activities [6].
  4. B. Remaining duration covers the work still to do; Original is the plan [1][2].
  5. B. Fixed Units holds the 800 hours, so the rate becomes 800 ÷ 20 = 40 h/d, five workers [3].

Key terms

Original duration
The planned working time from planned start to planned finish.
Remaining duration
Working time left from the remaining start to the remaining finish; zero when complete.
At Complete duration
Actual plus remaining working time; the current forecast of the activity's total length.
Units
The total amount of work on an assignment, usually in hours.
Units/Time
The rate at which a resource works on an assignment, such as 32 hours a day or 4 workers.
Duration type
The setting that decides whether P6 recalculates duration, units or units/time when one of them changes.

References

  1. Oracle. Enter activity durations. Primavera P6 Professional Help, Version 26.
  2. Oracle. Durations Columns of the Activity Table. Primavera P6 EPPM Help, Version 26.
  3. Oracle. Synchronizing activity duration, units, and resource units/time. Primavera P6 Professional Help, Version 26.
  4. Oracle. General Columns of the Activity Table. Primavera P6 EPPM Help, Version 26.
  5. Oracle. Define activity duration types. Primavera P6 Professional Help, Version 26.
  6. Oracle. Set the project default activity duration type. Primavera P6 Professional Help, Version 26.
  7. Oracle. Dates and Durations tab - Check Schedule dialog box. Primavera P6 Professional Help, Version 26.

Verified on November 6, 2026.

Next lesson in this trackRelationships and lags

PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. Oracle and Primavera are trademarks of Oracle. Microsoft Project is a trademark of Microsoft. BRC Academy is not affiliated with or endorsed by these organizations.

← All BRC Academy lessons

Have a program that's slipping, or about to start?

Book a 30-minute call. We'll tell you where your schedule and budget are exposed, and what an owner's rep would change, before you commit to anything.