BRC Academy · PMBOK® Guide 8

Focus area: Executing

Executing is where most of the money is spent. On a stipulated-price building project the contractor does the building, so owners sometimes assume the Executing focus area belongs to someone else. It does not. The PMBOK® Guide, Eighth Edition, from PMI®, puts eight processes in Executing, and an owner team runs every one of them on its own side of the contract. This lesson explains each, separates owner work from contractor work, and sets up an execution rhythm for Northgate.

Learning outcomes

  • List the eight Executing processes and the performance domain each belongs to.
  • Separate what the owner executes from what the contractor executes under a CCDC 2-2020 stipulated price contract.
  • Distinguish quality assurance from quality control and place each in a construction example.
  • Set an owner's execution rhythm of meetings, logs and reports for Northgate (fictional).

The lesson

What the Executing focus area covers

Executing turns the plan from lesson 13 into deliverables and outcomes. In the Eighth Edition it holds eight of the 40 processes, drawn from four of the seven performance domains (Figure 1). Governance contributes three, Stakeholders two, Resources two and Risk one. Scope, Schedule and Finance have no Executing process at all: the work itself produces scope, consumes time and spends money, and those domains watch it through Monitoring and Controlling instead.

The eight Executing processes by performance domain Four domain groups. Governance: Manage Project Execution, Manage Quality Assurance, Manage Project Knowledge. Stakeholders: Manage Stakeholder Engagement, Manage Communications. Resources: Acquire Resources, Lead the Team. Risk: Implement Risk Responses. Scope, Schedule and Finance have no Executing process. Governance (3) Manage Project Execution Manage Quality Assurance Manage Project Knowledge Stakeholders (2) Manage Stakeholder Engagement Manage Communications Resources (2) Acquire Resources Lead the Team Risk (1) Implement Risk Responses Scope, Schedule, Finance (0) No Executing process. The work produces scope and spends time and money; these domains watch it in M&C.
Figure 1. Executing holds eight processes from four domains; Governance supplies the most. Source: BRC, based on published PMBOK Guide 8 process maps (Project Together Office; Mudassir Iqbal).

Manage Project Execution: directing the work

This Governance process is about leading the planned work and putting approved changes into effect. On an owner's project it has a sharp boundary. Under CCDC 2-2020 the contractor controls the means and methods of construction, so the owner does not direct how Halvorsen pours a slab. What the owner directs is its own scope: its consultants, its permits and approvals, its separate contracts such as racking, IT and furniture, and its decisions. The owner reaches the contractor's work only through the contract's instruments: the Consultant's instructions, Change Orders and Change Directives. When an owner's PM starts giving site instructions directly to trades, execution has slipped out of governance and into a claim.

Manage Quality Assurance is not inspection

The Eighth Edition keeps a clear line between assurance and control. Quality assurance asks whether the processes being followed will produce work that meets requirements. Quality control checks the product itself: the test, the inspection, the measurement. In construction, a concrete cylinder test is control. Confirming that an inspection and test plan exists, that it covers the right hold points, that the testing agency is qualified and that results reach the right people quickly is assurance.

Owners are often better placed to do assurance than control. The Consultant and testing agencies perform most of the checks; the owner's job is to make sure the system that runs those checks is working. This is the "embed quality" principle from lesson 8 in practice.

Quality assurance compared with quality control on a slab pour Two columns. Quality assurance asks whether the process will work: inspection and test plan approved, hold points agreed, testing agency qualified, results routed within agreed time. Quality control asks whether the product meets requirements: slump and air tests at the truck, cylinder breaks at 7 and 28 days, slab flatness survey, Consultant field review. An arrow shows control results feeding back to improve assurance. Quality assurance Will the process work? • Test plan approved • Hold points agreed • Testing agencyqualified • Results routedwithin agreed time Owner leads Quality control Does the product meet it? • Slump and air tests • Cylinder breaks,7 and 28 days • Flatness survey • Consultant fieldreview Contractor, agency,Consultant perform Control results show where the process needs fixing
Figure 2. Assurance checks the system; control checks the product. Examples are typical of a slab-on-grade pour, not a specification. Source: BRC, based on the Manage Quality Assurance process as summarized by Project Management Compass.

Manage Project Knowledge

Projects learn things that are easy to lose: why a substitution was accepted, what the City's inspector asked for, which supplier is slow to respond. Manage Project Knowledge covers both explicit knowledge, the kind you can write down, and tacit knowledge, which lives in people. For an owner, the practical tools are a decision log, an RFI and submittal register the owner can search, and lessons captured as they happen rather than at close-out when half the team has moved on.

Stakeholders and communications

Manage Stakeholder Engagement is the active work of keeping the right people involved: the sponsor, the future warehouse operator, the City, neighbours, the lender. Manage Communications is the delivery of information under the communications plan. They differ. Sending a monthly report is communications; sitting down with the operations director to agree the racking layout before it is frozen is engagement.

Resources and the team

Acquire Resources brings in the people, services and materials the owner needs, at the time the plan says. Lead the Team covers direction, motivation, conflict and collaboration across a team that is often spread across several companies. On owner projects, the team is the owner's PM, the owner's representative, the Consultant and the owner's other advisers, not the contractor's workforce.

Implement Risk Responses

Planning wrote the response; Executing carries it out when the trigger arrives. The separate process exists because responses are often agreed and then never done. Each response needs a named owner, a trigger and evidence that it was carried out.

Northgate worked example

Northgate Distribution Centre (fictional) is a 12,000 m² tilt-up warehouse in Vaughan. Halvorsen Builders Ltd. (fictional) builds it under CCDC 2-2020 for $34,950,000, and Ridgeline Architects Inc. (fictional) is the Consultant under OAA 600. See the Northgate fact sheet. Between mobilization (M3, Monday March 1, 2027) and panels erected (M5, Friday June 25, 2027), the three parties each run their own execution, as Figure 3 shows.

Who executes what on Northgate Three stacked lanes. Northgate Logistics, the owner: direct owner contracts such as racking, make decisions on time, run quality assurance, keep the decision log, engage the operator and the City, carry out owner risk responses. Ridgeline, the Consultant: field reviews, review submittals and answer RFIs, issue instructions, certify payment. Halvorsen, the contractor: means and methods, subcontracts, quality control, site safety, schedule updates in P6. Arrows show the owner reaches Halvorsen's work only through the contract instruments. Northgate Logistics (owner) • Direct owner contracts (racking, IT) • Decide on time; keep the decision log • Run quality assurance • Engage operator, City, lender • Carry out owner risk responses decisions, changes Ridgeline (Consultant) • Field reviews • Review submittals; answer RFIs • Issue instructions; draft Change Orders • Certify payment contract instruments Halvorsen (contractor) • Means and methods; subcontracts • Quality control; site safety • Schedule updates in Primavera P6
Figure 3. Each party executes its own work. The owner reaches the contractor's work through the Consultant and the contract, not by direct site instruction. Simplified. Source: BRC, based on the Northgate fact sheet and the roles in CCDC 2-2020.

An execution rhythm

Most of the owner's Executing processes ride on a repeating cycle. Figure 4 shows an illustrative four-week rhythm the Northgate owner team could use during construction. Each meeting has one job. The weekly owner huddle runs Lead the Team and Manage Project Knowledge: decisions due, log updates, who is chasing what. The biweekly site meeting with Ridgeline and Halvorsen is where engagement and communications happen with the people doing the work. The monthly cycle ties the payment application, Halvorsen's Oracle Primavera P6 update and the owner's Microsoft Project master schedule update into one report to the sponsor.

Illustrative four-week owner execution rhythm A grid of four weeks. Every week has an owner team huddle. Weeks 1 and 3 have a site meeting with Ridgeline and Halvorsen. Week 2 has a quality assurance check. Week 4 has the payment application, schedule update and sponsor report. Wk 1Wk 2Wk 3Wk 4 Owner huddle Site meeting QA check Pay app andschedules Sponsor report Illustrative cadence. Orange: monthly cycle feeding the sponsor.
Figure 4. An illustrative four-week owner execution rhythm during construction. Frequencies are a BRC suggestion, not a Northgate contract requirement. Source: BRC.
View the data
EventFrequencyMain process served
Owner team huddleWeeklyLead the Team; Manage Project Knowledge
Site meeting with Ridgeline and HalvorsenEvery two weeksManage Stakeholder Engagement; Manage Communications
Quality assurance checkMonthlyManage Quality Assurance
Payment application and schedule updatesMonthlyManage Project Execution (feeds Monitoring and Controlling)
Sponsor reportMonthlyManage Communications

A risk response, carried out

Lesson 13 found that the owner's racking start (M10, Monday January 17, 2028) sits one working day after Ready-for-Takeover (M9, Friday January 14, 2028). Suppose the owner's risk register, as an illustrative entry, says: "Racking lead time could delay M10. Response: award the racking contract early enough that delivery is confirmed before M8 (commissioning starts Monday November 1, 2027). Trigger: no award by the date set in the plan." Implement Risk Responses is the owner's PM checking that date, and awarding the contract or escalating, rather than noting the risk again at the next meeting.

Owner's move

  • Direct your own work, not the contractor's. Route every instruction to Halvorsen through Ridgeline and the contract.
  • Audit the quality system early. Check the inspection and test plan before the first pour, not after the first failed test.
  • Give every meeting one job. Huddles for decisions, site meetings for coordination, the monthly cycle for reporting.
  • Write decisions down the day they are made. The decision log is the owner's memory when people change.
  • Close the loop on risk responses. A response is done when there is evidence, not when it is discussed.

Common mistakes

  1. Thinking Executing is only the contractor's job. The owner runs eight processes of its own.
  2. Calling inspections "QA". Inspections are control; assurance checks the system that runs them.
  3. Instructing trades directly. It undermines the Consultant and invites a claim.
  4. Confusing reporting with engagement. A report informs; engagement changes what people do or decide.
  5. Leaving lessons learned for close-out. By then the knowledge has left with the people.

Quick quiz

  1. How many processes sit in the Executing focus area of PMBOK Guide 8?

    1. 5
    2. 8
    3. 10
    4. 19
  2. Which domain has no Executing process?

    1. Governance
    2. Resources
    3. Schedule
    4. Risk
  3. The owner's PM confirms the concrete testing agency is qualified and that results reach Ridgeline within two days. Which process is this?

    1. Manage Quality Assurance
    2. Monitor and Control Project Performance
    3. Validate Scope
    4. Manage Project Knowledge
  4. Under CCDC 2-2020, how should Northgate's owner change the way Halvorsen sequences panel erection?

    1. Instruct the panel subcontractor on site
    2. It cannot; means and methods are the contractor's, though the owner can seek a change through the contract
    3. Revise Halvorsen's P6 file
    4. Issue a stop-work order
  5. Which activity is engagement rather than communications?

    1. Emailing the monthly report
    2. Posting meeting minutes
    3. Agreeing the racking layout with the operations director
    4. Updating the RFI register
Show answers and explanations
  1. B. Eight: three Governance, two Stakeholders, two Resources and one Risk.
  2. C. Scope, Schedule and Finance have no Executing process; they are watched through Monitoring and Controlling.
  3. A. It checks that the quality system works, which is assurance.
  4. B. The contractor controls means and methods. The owner can propose a change through Ridgeline and the contract's change provisions.
  5. C. Engagement involves the stakeholder in a decision; the others deliver information.

Key terms

Executing focus area
The PMBOK Guide 8 processes that carry out the plan and produce deliverables.
Quality assurance
Work that gives confidence the processes will produce results that meet requirements.
Quality control
Checks on the product itself, such as tests, inspections and measurements.
Means and methods
How the contractor chooses to build the Work; under CCDC 2-2020, the contractor's responsibility.
Explicit and tacit knowledge
Knowledge that can be written down, and knowledge held in people's experience.
Decision log
A dated record of each owner decision, who made it and why.

References

  1. Project Management Institute, PMBOK® Guide, Eighth Edition (product page; published November 2025).
  2. Project Together Office, PMBOK 8 focus areas: all 40 processes.
  3. Mudassir Iqbal, PMBOK 8 focus areas and 40 processes explained.
  4. Project Management Compass, Inside PMBOK® 8: Governance performance domain.
  5. Project Management Academy, What is PMBOK 8?
  6. Learning Tree, PMBOK® Guide 8th Edition: the complete guide to what's new.
  7. PM Exams, PMBOK 8 focus areas.

Verified on November 6, 2026.

Next lesson in this trackFocus area: Monitoring and Controlling

PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. Oracle and Primavera are trademarks of Oracle. Microsoft Project is a trademark of Microsoft. BRC Academy is not affiliated with or endorsed by these organizations.

← All BRC Academy lessons

Have a program that's slipping, or about to start?

Book a 30-minute call. We'll tell you where your schedule and budget are exposed, and what an owner's rep would change, before you commit to anything.