BRC Academy · PMBOK® Guide 8

Focus area: Initiating

The PMBOK® Guide, Eighth Edition, from PMI®, groups its processes into five focus areas, and Initiating is the first. It answers three questions before serious money is spent: why are we doing this, who is authorizing it, and who cares about it? For an owner, Initiating happens more than once. It happens when the project is approved, and it happens again at the start of each phase, including the weeks between tender close and the construction kickoff.

Learning outcomes

  • Name the five focus areas and explain why they are not the same as project phases.
  • Describe the purpose of the Initiating focus area and the two processes most closely tied to it.
  • Draft a one-page phase charter for an owner's construction phase.
  • Plan the initiating work for Northgate's construction phase between tender close and kickoff.

The lesson

Focus areas, not phases

The Eighth Edition brings back process guidance that the Seventh Edition had dropped, in a deliberately less prescriptive form: 40 processes, each described by inputs, tools and techniques, and outputs. They are organized two ways. By performance domain (governance, scope, schedule, finance, stakeholders, resources and risk), and by focus area: Initiating, Planning, Executing, Monitoring and Controlling, and Closing. Lesson 3 showed how the layers fit together.

Readers who studied for the PMP® exam on the Sixth Edition will recognize the five names from the old process groups. The intent is similar, but the framing has shifted: focus areas describe the kind of attention a piece of work needs, not a stage the project passes through once. A focus area can repeat, overlap with others and loop back. A project in construction is mostly executing and controlling, but when a new phase or a major new package starts, initiating work happens again. Treating focus areas as phases is a common misreading.

Focus areas repeat inside each phase Three phase bands stacked vertically: design, procurement, construction. Each band contains the same five focus area chips in a row: I for Initiating, P for Planning, E for Executing, M for Monitoring and Controlling, C for Closing. The Initiating chip is orange in every band. An arrow from Monitoring and Controlling loops back to Planning in each band. A note says Initiating happens at the start of every phase, not only once. Design phase Procurement phase Construction phase I P E M&C C I P E M&C C I P E M&C C I Initiating · P Planning · E Executing M&C Monitoring and Controlling · C Closing
Figure 1. Focus areas repeat inside each phase, and monitoring loops back to planning. Initiating (orange) opens every phase. Phase names are a typical owner's design-bid-build sequence. Source: BRC, based on the focus area structure of the PMBOK Guide, Eighth Edition (paraphrased; not a PMI figure).

What Initiating is for

Initiating work defines and authorizes a project or a phase. In plain terms it produces four things:

  • A reason: the business need and the outcomes the project or phase must deliver, tied back to the business case (lesson 7 covered outcomes versus outputs).
  • Authority: a named sponsor who commits funds, and a named project manager with stated authority.
  • Boundaries: high-level scope, key milestones, budget, constraints and assumptions, and what is out of scope.
  • People: who is affected, who can influence the result, and what they expect.

Initiating is short compared with planning, but it sets the frame planning works inside. A phase that starts without a clear sponsor or success criteria will spend its planning effort arguing about what it is for.

The two processes most tied to Initiating

Published summaries of the 40 processes list an Initiate Project or Phase process in the governance domain and an Identify Stakeholders process in the stakeholders domain. These are the two that carry the initiating work described above. Initiate Project or Phase produces the authorizing document, traditionally called the project charter, which formally starts the project or phase and gives the project manager authority to use resources. Identify Stakeholders produces a list of the people and organizations involved or affected, with their interests and influence, usually called a stakeholder register. Both are revisited later: stakeholders are identified throughout the project, and a phase charter is reissued for each phase.

Notice the domains. The charter sits in governance, which the Eighth Edition made a domain of its own, and that placement says something: the charter is a governance instrument. It records who decided to proceed and on what terms, and it is the yardstick for later decisions about change.

Initiating on the owner's side

On a design-bid-build building project, the owner initiates the whole project long before design, with a business case and approval to spend. Then it initiates each phase. The construction phase is a big one: the contract is about to be signed, the owner's team grows, and new stakeholders arrive (the contractor, its trades, the municipality's inspectors, neighbours). The construction phase charter is the owner's internal document. It does not replace the contract; it states what the owner is trying to achieve with it and who on the owner's side can decide what.

Northgate worked example

Northgate Distribution Centre (fictional) is a $38.0 million construction budget for Northgate Logistics Inc. (fictional): a $34,950,000 CCDC 2-2020 Contract Price with Halvorsen Builders Ltd. (fictional) and a $3,050,000 owner contingency, with Ridgeline Architects Inc. (fictional) as prime consultant. Facts are from the Northgate fact sheet.

The initiating window

Tender closed on Tuesday December 8, 2026. The contract is executed at M0, Monday January 11, 2027, and the kickoff meeting is M1, Tuesday January 19, 2027. The owner's construction-phase initiating work fits into those six weeks. Figure 2 shows a plan; the intermediate dates are illustrative. The handoff content itself is covered in the construction-phase track (handoff and kickoff lessons).

Northgate construction-phase initiating window A vertical timeline from December 8, 2026 to January 19, 2027. Tuesday December 8, 2026: tender closed. Friday December 18: award recommendation to sponsor, illustrative. Monday January 11, 2027: M0, contract executed. Thursday January 14: stakeholder register first issue, illustrative. Friday January 15: construction-phase charter signed by sponsor, illustrative. Tuesday January 19: M1, kickoff meeting; charter shared with Ridgeline and Halvorsen in summary. Not to scale. * = illustrative date. Tue Dec 82026 Tender closedBids evaluated Fri Dec 18* Award recommendationSponsor approves proceeding Mon Jan 112027 M0: contract executedCCDC 2-2020 with Halvorsen Thu Jan 14* Stakeholder registerFirst issue Fri Jan 15* Phase charter signedBy the Northgate sponsor Tue Jan 19 M1: kickoff meetingCharter summary shared Initiating ends; Planning (baseline) takes over.
Figure 2. Northgate's construction-phase initiating window. Tender close, M0 and M1 are baseline facts; the starred dates are illustrative. Source: BRC, based on the Northgate fact sheet.
View the data
DateEventStatus
Tue Dec 8, 2026Tender closedFact sheet
Fri Dec 18, 2026Award recommendation to sponsorIllustrative
Mon Jan 11, 2027M0: contract executedFact sheet
Thu Jan 14, 2027Stakeholder register, first issueIllustrative
Fri Jan 15, 2027Construction-phase charter signedIllustrative
Tue Jan 19, 2027M1: kickoff meetingFact sheet

The order matters. The sponsor signs the phase charter before kickoff so that the owner's project manager walks into M1 with authority already settled: what they can approve, which milestones the owner is holding Halvorsen to, and who the owner's decision-makers are. Signing the charter after M0 is fine: the contract fixes Halvorsen's obligations, and the charter fixes the owner's internal ones.

A one-page phase charter

Figure 3 shows the sections of Northgate's construction-phase charter. Everything on it comes from the fact sheet except the authority limits, which are illustrative and match the decision-rights matrix in lesson 9.

Northgate construction-phase charter on one page A one-page document outline with eight sections. Purpose: deliver a 12,000 square metre distribution centre ready for racking on January 17, 2028. Success criteria: Ready-for-Takeover and Substantial Performance at M9 January 14, 2028; within the $38.0 million construction budget; zero lost-time injuries. Key milestones: M0 to M11. Budget: Contract Price $34.95 million plus contingency $3.05 million. Authority: owner's PM approves changes up to $50,000 from contingency, illustrative; sponsor above. Key stakeholders: see stakeholder register. Assumptions and constraints: CCDC 2-2020, Ontario statutory holidays, separate racking contract. Approval: sponsor signature and date. NDC construction-phase charter 1. Purpose Warehouse ready for racking on M10, Jan 17, 2028 2. Success criteria RFT and SP at M9, Fri Jan 14, 2028 Within the $38.0M construction budget Zero lost-time injuries (owner goal) 3. Key milestones M0 to M11, per the owner's master schedule 4. Budget Contract Price $34.95M + contingency $3.05M 5. Authority Owner PM: changes to $50,000* from contingency Sponsor: above $50,000* and early occupancy 6. Key stakeholders See stakeholder register (first issue Jan 14*) 7. Assumptions and constraints CCDC 2-2020; Mon to Fri, Ontario stat holidays; racking under a separate owner contract 8. Approval Sponsor signature and date * illustrative
Figure 3. The sections of a one-page construction-phase charter for Northgate. Sections and wording are BRC's, not a PMI template. Authority limits and the safety goal are illustrative. Source: BRC, based on the Northgate fact sheet and the Initiate Project or Phase process as summarized in third-party guides.

The first stakeholder register

The construction phase brings stakeholders the design phase barely touched. A first register for Northgate would include the Northgate sponsor and operations team; Ridgeline and its subconsultants; Halvorsen and its key trades; the City of Vaughan building department; the racking supplier under the owner's separate contract; the owner's insurer (which cares about the ESFR sprinkler system); utilities for permanent power at M7; and neighbours affected by truck traffic. For each, the register records their interest, their influence and the owner's contact. It will grow; the point of issuing it at initiation is to stop the obvious ones from being forgotten.

Owner's move

  • Initiate each phase, not just the project. Issue a short phase charter at the start of design, procurement and construction.
  • Sign before kickoff. Have the sponsor approve the construction-phase charter before M1 so authority is settled when the team meets.
  • Make success measurable. Use milestone dates, budget figures and safety goals, not "deliver a quality building".
  • Write down the assumptions. Separate contracts, calendars and permits belong in the charter, where they can be tested later.
  • Start the register early. Issue the first stakeholder register in the initiating window and update it at each phase.

Common mistakes

  1. Treating focus areas as phases. Initiating is not "done" once the project is approved; each phase needs it.
  2. Letting the contract stand in for the charter. The contract binds the contractor; the charter binds the owner's own team.
  3. A charter without authority. Naming a project manager without stating what they can approve.
  4. Vague success criteria. If nobody can say whether the phase succeeded, nobody can steer it.
  5. A stakeholder list of only the contract parties. Municipalities, insurers, utilities and neighbours drive real risk.

Quick quiz

  1. Which list names the five focus areas of the Eighth Edition?

    1. Governance, scope, schedule, finance, risk
    2. Initiating, Planning, Executing, Monitoring and Controlling, Closing
    3. Concept, design, tender, build, close
    4. Value, quality, leadership, sustainability, culture
  2. How do focus areas differ from phases?

    1. They are identical
    2. Focus areas can repeat and overlap within each phase
    3. Focus areas happen once, in order
    4. Phases are optional, focus areas are not
  3. Which performance domain holds the Initiate Project or Phase process in published summaries?

    1. Scope
    2. Finance
    3. Governance
    4. Risk
  4. What does a phase charter give the owner's project manager?

    1. Control of the contractor's means and methods
    2. Formal authority to apply resources to the phase
    3. The right to certify payment
    4. A replacement for the contract
  5. Why sign Northgate's construction-phase charter before M1?

    1. The contract requires it
    2. So authority is settled before the team meets
    3. To delay the kickoff
    4. So Halvorsen can sign it
Show answers and explanations
  1. B. Option A lists performance domains; option D lists principles.
  2. B. Focus areas describe the kind of work, which recurs; phases are stages in time.
  3. C. The charter is a governance instrument, and the process sits in the governance domain.
  4. B. The charter authorizes the phase and the project manager's use of resources; it cannot override CCDC 2 roles.
  5. B. The kickoff is where commitments are made; the owner's side should know its limits first.

Key terms

Focus area
One of five groupings of PMBOK Guide 8 processes by the kind of attention work needs: Initiating, Planning, Executing, Monitoring and Controlling, Closing.
Initiating
The focus area that defines and authorizes a project or phase.
Project charter
The document that formally authorizes a project or phase and the project manager's authority.
Phase charter
A charter issued for one phase, such as construction, within an approved project.
Stakeholder register
A list of people and organizations involved in or affected by the project, with their interests and influence.
Sponsor
The person who provides funding and authority for the project and is accountable for its business case.

References

  1. Project Management Institute, PMBOK® Guide, Eighth Edition (product page: seven performance domains, reintroduced non-prescriptive processes).
  2. PMExams, PMBOK 8: the full process map (third-party summary of the 40 processes by performance domain).
  3. PMExams, PMBOK 8 focus areas (focus areas recur and overlap; not phases).
  4. 4PMTI, What is the PMBOK 8th edition? Principles, domains, focus areas, and what changed.
  5. Mark Whitfield, PMBOK Guide 8th edition (May 2026; five focus areas, 40 processes with inputs, tools and techniques, and outputs).

Verified on November 6, 2026.

Next lesson in this trackFocus area: Planning

PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. Oracle and Primavera are trademarks of Oracle. Microsoft Project is a trademark of Microsoft. BRC Academy is not affiliated with or endorsed by these organizations.