BRC Academy · Contracts

Why the contract is the owner's #1 risk tool

Every construction project carries risk: ground that is worse than expected, a late permit, a supplier that fails, a design that does not fit. The owner cannot remove those risks. What the owner can do is decide, before anyone signs, who carries each one, at what price and with what paperwork. The contract is where that decision is written down, and it is the one risk tool that still works after things go wrong.

Learning outcomes

  • Explain why the construction contract is an owner's main risk tool, and how it differs from a risk register or insurance alone.
  • Describe how an unamended CCDC 2-2020 splits common risks between owner and contractor, with the General Condition (GC) that governs each.
  • Follow the five steps that take a risk from the register into the contract and then into day-to-day management.
  • Spot the owner's decisions on Northgate that have to be made before tender, not after.

The lesson

A contract is a risk allocation, written in advance

Owners often think of the contract as the price and the scope. Those matter, but the more useful way to read a construction contract is as a list of answers to the question "what happens if?" What happens if the soil is soft? If the roofing supplier goes bankrupt? If the city stops the job? If the owner changes its mind about the office layout? Each answer moves money and time from one party to the other.

That is why the contract is the owner's first risk tool and not just one of many. A risk register records risks. A contingency budget pays for them. Insurance transfers some of them to an insurer. But only the contract decides, in a way that binds the other party, which risks the contractor has priced into its bid and which ones come back to the owner as change orders, time extensions and claims. If the contract is silent or vague, the answer gets decided later, usually by negotiation under pressure, by an adjudicator or by a court.

The price you pay depends on the risk you hand over

Contractors are not charities, and good ones are not reckless. When a tender asks a contractor to carry a risk, it prices that risk into the bid, adds a premium for uncertainty, or declines to bid. When the owner keeps a risk, the bid comes in lower, but the owner must budget for the risk and manage it.

The usual principle is that a risk should sit with the party best able to control it or absorb it. The contractor controls its own crews, methods, safety and subcontractors, so those risks sit naturally with it. The owner controls the design, the site it bought and the decisions it makes during construction, so those sit naturally with the owner. Some risks belong to nobody, such as a province-wide strike or a fire that neither party caused, and contracts usually share them: the contractor gets time but not money.

Pushing every risk onto the contractor through one-sided Supplementary Conditions looks protective on paper. In practice it raises bids, narrows the bidder list and invites claims when the contractor tries to recover what it could not price. A good contract is not the most one-sided one. It is the one where each risk has a clear owner, a clear price and a clear process.

How a standard CCDC 2-2020 splits common risks

Most Canadian stipulated price work uses CCDC 2-2020, the Canadian Construction Documents Committee's stipulated price contract. The standard form is a balanced starting point negotiated by owners, contractors, consultants and lawyers. Figure 1 shows how the unamended form places ten common risks. Later lessons go clause by clause; this is the map.

Who carries which risk under an unamended CCDC 2-2020 Ten common risks placed in three columns: owner, shared and contractor. The contractor carries price, means and methods, and warranty defects. Delay beyond either party's control and third-party claims are shared. The owner carries design errors, concealed conditions that are materially different, owner-caused delay, pre-existing toxic substances, and permits and work by its own forces. Owner Shared Contractor Risk Where it sits in the contract Price of the defined Work Stipulated Contract Price Means, methods and site safety GC 3.1; OHSA constructor Defects found in warranty GC 12.3, from RFT Delay beyond either party's control GC 6.5.3: time, no cost Third-party injury and damage GC 13.1: each its share Errors in the owner's design Contract Documents Concealed or unknown conditions GC 6.4, if materially different Owner- or consultant-caused delay GC 6.5.1: time and cost Pre-existing toxic substances GC 9.2 Permits and work by owner's forces GC 10.2; GC 3.2
Figure 1. Who carries which risk under an unamended CCDC 2-2020. Simplified for teaching; the exact wording, conditions and any Supplementary Conditions decide the real answer. Source: BRC, based on CCDC 2-2020 commentary from Osler, C. Wilson Law, Norton Rose Fulbright, TDS Law and the OAA.
View the data
RiskWhere it sitsCarried by
Price of the defined WorkStipulated Contract PriceContractor
Means, methods and site safetyGC 3.1; OHSA constructorContractor
Defects found in warrantyGC 12.3, from RFTContractor
Delay beyond either party's controlGC 6.5.3: time, no costShared
Third-party injury and damageGC 13.1: each its shareShared
Errors in the owner's designContract DocumentsOwner
Concealed or unknown conditionsGC 6.4, if materially differentOwner
Owner- or consultant-caused delayGC 6.5.1: time and costOwner
Pre-existing toxic substancesGC 9.2Owner
Permits and work by owner's forcesGC 10.2; GC 3.2Owner

A few of these deserve a closer look, because they are where owners are most often surprised.

Concealed or unknown conditions (GC 6.4). If either party finds subsurface or hidden conditions that differ materially from what the Contract Documents show, or from what is normal for the area, it must give written notice promptly; the standard window is five working days. The Consultant investigates and, if the difference is material, the Contract Price and Contract Time are adjusted through a Change Order or Change Directive. In plain terms, the owner carries the ground. A geotechnical report and a contingency are how the owner manages that.

Delay (GC 6.5). The form treats delay according to cause. Where the owner, the Consultant or someone they are responsible for causes delay, the contractor gets an extension and its reasonable costs (GC 6.5.1). Where delay comes from causes beyond the contractor's control and not the owner's fault, such as labour disputes or fire, the contractor gets time but not money (GC 6.5.3). The 2020 edition also narrowed relief for stop-work orders from a court or public authority (GC 6.5.2). Lesson 26 covers delay clauses in detail.

Toxic and hazardous substances (GC 9.2). Substances already on site before the contractor arrived, such as contaminated fill or asbestos in an existing structure, generally stay the owner's responsibility. The contractor must stop and report; the owner must deal with it and, in many cases, pay for the delay.

Insurance (GC 11.1) and indemnities (GC 13.1). CCDC 2-2020 ties the insurance period, the warranty period (GC 12.3) and the indemnity timelines to the new Ready-for-Takeover milestone instead of Substantial Performance. It also raised the standard general liability limit from $5 million to $10 million and added pollution liability. Under GC 13.1, neither party is liable to the other for indirect or consequential losses, which matters to an owner that would lose rent or operating revenue if the building is late.

Waiver of claims (GC 13.2). After Ready-for-Takeover, each party gives up claims it has not given notice of within set periods, with exceptions such as substantial defects noticed within six years. This is the contract quietly closing the door. An owner that does not track defects and give notice on time can lose rights it never knew it had.

Your leverage is highest before you sign

Figure 2 shows the idea every owner's rep repeats. While the owner is drafting the contract and the tender is open, it can decide any allocation it wants at almost no cost; bidders simply price what they see. Once the contract is signed, every change to the deal needs the contractor's agreement, and every change during construction costs money and time. By closeout, the contract is mostly being enforced, not shaped.

The owner's leverage over risk falls as the cost of changing course rises Illustrative curves across six stages from planning to closeout. The owner's ability to shape risk allocation is highest while the contract is being drafted and falls sharply after signing. The cost of changing the deal is low early and rises steeply during construction. Owner's leverage over risk Cost of change Contract signed Plan Draft Tender Sign Build Close Northgate: tender closed Dec 8, 2026; contract signed Jan 11, 2027; construction Mar 2027 to Jan 2028.
Figure 2. The owner's leverage over risk falls as the cost of changing the deal rises. Illustrative only: relative levels, not to scale; the curves show direction, not measured values. Source: BRC, based on the Northgate fact sheet (fictional) and common project-controls practice.

This is why the contract work that matters most happens in the months before tender: choosing the delivery method and form, writing the Supplementary Conditions, deciding which reports to include, setting allowances and cash allowances, and writing the schedule and payment specifications. After award, the owner's job shifts from shaping the risk to managing it.

From risk register to contract clause

Risk management and contract drafting are often done by different people who never compare notes. The risk register sits with the project manager; the contract sits with legal and procurement. Figure 3 shows how they should connect.

From risk register to contract clause in five steps Five steps: identify the risk, allocate it to the party best placed to carry it, write the allocation into the contract documents, price it through contingency, allowances or insurance, and manage it through notice and the change process. Each step shows the Northgate subsurface-conditions example. 1 Identify List the risks the project actually faces. Northgate: clay and fill under the slab 2 Allocate Decide who can best control or absorb each one. Owner keeps it: GC 6.4 applies 3 Write it in Agreement, GCs, Supplementary Conditions, specs. Geotech report issued with the tender 4 Price it Contingency, allowances, insurance, bonds. Part of the $3.05M contingency 5 Manage it Notice, records and the change process. 5-working-day notice, consultant decides
Figure 3. Five steps from risk register to contract clause, with the Northgate subsurface example (fictional). Step 3 is where most owners leave gaps. Source: BRC, based on CCDC 2-2020 GC 6.4 as summarized by C. Wilson Law.

For every major risk on the register, the owner should be able to answer five questions. What is the risk? Who carries it under the contract? Which document says so: the Agreement, a GC, a Supplementary Condition or a specification section? How is it paid for: in the contractor's price, the owner's contingency, an allowance, insurance or a bond? And what process triggers relief: which notice, within how many days, to whom, with what records? If any answer is "we're not sure", that risk has not really been allocated.

Statute sits above the contract

In Ontario, some allocations are not up to the parties. The Construction Act sets holdback, lien rights, prompt payment timelines and adjudication, and contract terms cannot contract out of them. The Occupational Health and Safety Act assigns duties to the constructor whatever the contract says. A good contract works with these rules; a contract that ignores them creates false comfort. Lessons 23 and 24 cover prompt payment and holdback.

Northgate worked example

The Northgate Distribution Centre (fictional) is a 12,000 m² tilt-up warehouse in Vaughan for Northgate Logistics Inc. (fictional), delivered design-bid-build under CCDC 2-2020 with a Contract Price of $34.95 million and an owner contingency of $3.05 million. Tender closed on December 8, 2026 and the contract is executed on January 11, 2027. Before tender, the owner's representative ran a contract risk review. Five of the risks it worked through show how the contract does the work.

RiskStandard CCDC 2-2020 answerOwner's decision before tender
Soft clay or old fill under the 12,000 m² slabOwner carries materially different conditions (GC 6.4)Issue the geotechnical report with the tender for information, ask bidders to price the subgrade preparation it describes, and hold part of the contingency for the rest.
Building permit not issued in time (target Feb 26, 2027, three days before mobilization on Mar 1)Permits for the building are the owner's side (GC 10.2); late permit is owner delay (GC 6.5.1)Treat the permit as an owner-critical milestone in the master schedule and allow a time buffer in the Contract Time rather than assuming it lands on time.
Spring casting and panel erection hit by unusual weatherTime, no money, if beyond the contractor's control (GC 6.5.3)Define in the Supplementary Conditions what counts as abnormal weather, so the argument is settled before the first wet week.
Owner's racking installer working in the building from Jan 17, 2028Work by owner's forces must be coordinated (GC 3.2)Name the racking scope in the tender, set the access date and confirm who is constructor during the overlap.
Steel and roofing price swings over a 14-month windowContractor carries price risk in a stipulated price unless the contract says otherwiseDecide deliberately: accept a higher bid with no escalation clause, or add a capped escalation clause for named materials. Either can be right; silence is not.

Notice the pattern. None of these decisions costs much on December 1, 2026. Every one of them is expensive to fix on June 1, 2027, when panels are being stood up and the contractor is pricing every gap in the documents as a change.

Owner's move

  • Demand a risk allocation table before tender. One page that lists the top 15 to 20 risks, who carries each one under the contract, the clause that says so, and how it is funded. If your consultant or lawyer cannot produce it, the contract has not been reviewed for risk.
  • Check the Supplementary Conditions against that table. Every amendment to the standard form should move a specific risk for a specific reason. Delete amendments copied from another project that nobody can explain.
  • Reject blanket risk transfer. Clauses that make the contractor responsible for "all conditions whatsoever" or waive every delay claim raise prices and seldom survive a dispute intact. Keep the risks you can manage and pay for the ones you transfer.
  • Put the notice clauses in the project's operating rules. GC 6.4's five working days and the delay notice periods should be in the kickoff agenda, the meeting minutes template and the owner team's checklist.
  • Get legal advice on the final form. Use a construction lawyer for the Supplementary Conditions, and an insurance broker for GC 11 and the bonding requirements.

Common mistakes

  1. Treating the contract as procurement paperwork. The form is filled in at the last minute by someone who was not in the risk workshop, so the register and the contract never meet.
  2. Over-amending the standard form. Heavy, one-sided Supplementary Conditions scare off good bidders and do not stop claims; they just change what the claims argue about.
  3. Leaving reports out of the tender. An owner that withholds a geotechnical or hazardous materials report does not shift the risk. It weakens its own position when conditions turn out to be different.
  4. Forgetting the owner's own obligations. Permits, owner-supplied equipment, timely decisions and payment are owner risks. Late owner decisions are one of the most common sources of compensable delay.
  5. Ignoring notice and waiver periods. Owners hold contractors to notice deadlines and then miss their own defect notices after Ready-for-Takeover.

Quick quiz

  1. Why is the contract described as the owner's main risk tool?

    1. It is the only document the contractor signs
    2. It binds both parties to a decision on who carries each risk and how relief is triggered
    3. It replaces the need for insurance
    4. It guarantees the project finishes on time
  2. Under an unamended CCDC 2-2020, materially different concealed site conditions are mainly whose risk?

    1. The contractor's, because the price is stipulated
    2. The consultant's
    3. The owner's, through an adjustment under GC 6.4
    4. Nobody's; they are excluded
  3. A fire that neither party caused delays the work. Under GC 6.5.3 the contractor usually gets:

    1. Time and money
    2. Money only
    3. Time but not money
    4. Nothing
  4. When is the owner's leverage over risk allocation highest?

    1. Before the contract is signed, while the tender is being prepared
    2. At the first progress payment
    3. At Substantial Performance
    4. During the warranty period
  5. Which is the best reason to avoid pushing every risk onto the contractor?

    1. The CCDC forbids any amendments
    2. Contractors price, or refuse, risks they cannot control, which raises bids and invites claims
    3. Insurance covers every risk anyway
    4. Ontario law makes the owner liable for all risks
Show answers and explanations
  1. B. The register and insurance help, but only the contract binds the other party to who carries each risk, at what price, and through which notice and change process.
  2. C. GC 6.4 provides for a price and time adjustment where conditions differ materially, after notice and the Consultant's investigation.
  3. C. For delays beyond the contractor's control that are not the owner's fault, the standard form gives a time extension without payment for the delay costs.
  4. A. Before signing, the owner can set any allocation and bidders price it. After signing, every change to the deal needs agreement and costs more.
  5. B. Risk you transfer is risk you pay for. Unmanageable transfers raise prices, reduce competition and tend to come back as disputes.

Key terms

Risk allocation
The contract's answer to who bears the cost and time impact of an event, and on what conditions.
CCDC 2-2020
The Canadian Construction Documents Committee's stipulated price contract, 2020 edition, the most common Canadian form for design-bid-build.
General Conditions (GCs)
The standard terms inside a CCDC form, cited by number, such as GC 6.4.
Supplementary Conditions
Project-specific amendments to the standard GCs. Lesson 10 covers how to write them.
Concealed or unknown conditions
Hidden or subsurface conditions that differ materially from what the documents show or what is normal in the area (GC 6.4).
Ready-for-Takeover (RFT)
The CCDC 2-2020 milestone, set out in GC 12.1, when the owner can take over the Work; it now starts the insurance, warranty and indemnity clocks.
Waiver of claims
The GC 13.2 mechanism by which each party gives up claims it has not noticed within the set periods.

References

  1. Osler, Hoskin & Harcourt LLP, "Introducing CCDC 2-2020." osler.com
  2. C. Wilson Law, "Changes in the Contract Work: CCDC 2's General Condition 6." cwilson.com
  3. Norton Rose Fulbright, "Canada: relief provisions in construction contract suites" (May 2020). nortonrosefulbright.com
  4. Bailey Harris, TDS Law, "10 Key Changes in the CCDC 2-2020" (February 14, 2022). tdslaw.com
  5. Lydia Roseman, McLennan Ross LLP, "The New CCDC 2 Stipulated Price Contract, Part II: Supplementary Conditions" (January 11, 2022). legal500.com
  6. Ontario Association of Architects, Practice Tip PT.23.11, "CCDC 2-2020: Overview of Changes." oaa.on.ca
  7. Canadian Construction Documents Committee, CCDC 2-2020 Stipulated Price Contract (purchase the form from CCDC or an authorized distributor). ccdc.org

Verified on November 4, 2026.

Next lesson in this trackCanada's standard forms: CCDC, CCA, OAA and RAIC

This lesson is general education, not legal advice. Get advice from a construction lawyer on your contract.

PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. Oracle and Primavera are trademarks of Oracle. Microsoft Project is a trademark of Microsoft. BRC Academy is not affiliated with or endorsed by these organizations.

← All BRC Academy lessons

Have a program that's slipping, or about to start?

Book a 30-minute call. We'll tell you where your schedule and budget are exposed, and what an owner's rep would change, before you commit to anything.