Value Engineering Done Right: A Guide for Building Owners

A workshop participant holding yellow sticky notes during an idea generation session

On many projects, "value engineering" means something very specific: the tender came in over budget, and now everyone is in a room crossing out finishes, deleting the canopy and swapping the specified equipment for something cheaper. That isn't value engineering. It's cost cutting under a better name, and it often costs more over the life of the building than it saves at tender.

Real value engineering is a structured method with a long track record. Done at the right time, it improves what the owner gets for the money. This guide explains what it is, how function analysis makes it different, when to do it, and how an owner should evaluate the proposals it produces.

What value engineering is

SAVE International, the main professional body for the discipline, describes value methodology as a structured process in which a cross-disciplinary team, led by a qualified facilitator, analyzes functions to improve value. It expresses value as a ratio: the performance of the functions the owner needs, divided by the resources (money and time) spent to get them.

That ratio is the point. Value can rise because cost falls, but it can also rise because performance improves for the same money. A proposal that cuts cost and also cuts a function the owner needs doesn't add value. It just moves the problem.

The U.S. Whole Building Design Guide, maintained by the National Institute of Building Sciences, is blunt about the distinction: value engineering is not a design peer review or a cost-cutting exercise. The U.S. Federal Highway Administration makes the same point in its guidance, describing VE as a way to add value and quality, not simply to reduce costs.

In Canada, Value Analysis Canada notes that value analysis, value engineering and value management describe the same method. The names differ by industry and era, not by substance.

Function analysis: the part that makes it different

What separates value engineering from a cost review is function analysis. Before anyone suggests alternatives, the team defines what each part of the project must do, stated as an active verb and a measurable noun. A storefront might "display merchandise" and "admit light." A loading dock canopy might "protect goods." A mechanical system might "condition air" and "control humidity."

Once functions are named, each one can be given a cost. That's often revealing. On programs we've supported, function analysis regularly shows a large share of cost tied up in secondary functions, such as appearance features nobody asked for or redundancy beyond the owner's actual requirements, while a basic function the owner cares about is underserved.

The Function Analysis System Technique (FAST) takes this further by mapping how functions relate. Asking "how?" moves toward the solution. Asking "why?" moves toward the owner's real objective. A canopy exists to protect goods, which exists to keep stock saleable. Once that chain is clear, the team can ask whether there's a better way to keep stock saleable, which is a much more useful question than how to make the canopy cheaper.

The job plan

Value engineering follows a fixed sequence called the job plan. SAVE International describes eight phases:

The eight-phase value methodology job plan SAVE International's job plan: preparation, information, function analysis, creativity, evaluation, development, presentation and implementation. Function analysis, the third phase, is what distinguishes value engineering from cost cutting. The value engineering job plan Eight phases, as described by SAVE International 1. Preparation Set scope, team and timing 2. Information Gather drawings, costs, constraints 3. Function analysis Name functions and their cost 4. Creativity Generate ideas; no judgment yet 5. Evaluation Screen ideas against criteria 6. Development Cost, LCC, risks for best ideas 7. Presentation Proposals to decision-makers 8. Implementation Accept, revise, build into design Function analysis comes before any ideas are generated
Phase names from SAVE International. Function analysis (highlighted) is the step most often skipped when VE turns into cost cutting. Diagram by Benjamin R. Consulting.
View the data
PhaseWhat happens
1. PreparationSet scope, team and timing
2. InformationGather drawings, costs, constraints
3. Function analysisName functions and their cost
4. CreativityGenerate ideas; no judgment yet
5. EvaluationScreen ideas against criteria
6. DevelopmentCost, LCC, risks for best ideas
7. PresentationProposals to decision-makers
8. ImplementationAccept, revise, build into design

The creative phase depends on keeping judgment out of it. Ideas are listed first and evaluated later, so the obvious answer doesn't crowd out the better one. The development phase is where ideas become proposals, with costs, life-cycle effects, drawings and risks set out so a decision-maker can accept or reject each one.

A typical study is a workshop of several days. The Whole Building Design Guide describes a workshop of about 40 hours, less for smaller projects. FHWA suggests a team of about five to eight people from different backgrounds generally works well. The team should include people independent of the design, alongside the designers who know why decisions were made.

Timing: early beats late

Value engineering can be done at any stage, but the return falls the later it starts. The Whole Building Design Guide notes that earlier application generally gives a higher return, and that changes at the planning stage have very little effect on schedule or redesign cost. FHWA's advice is to hold a study as soon as there's enough information, with an optional second study during final design.

The reason is simple. At concept stage, changing the structural system, the building form or the site layout costs a few weeks of design time. After construction documents are complete, the same change means redesign, re-coordination, new permit drawings and possibly re-tendering. By then, the only changes that pay for themselves are usually the small ones.

That's why VE done after a high tender so often turns into cost cutting. The study is too late to change anything fundamental, so it changes what's easy instead: finishes, equipment quality and scope.

Value engineering versus cost cutting

  • Starting point. VE starts from the functions the owner needs. Cost cutting starts from the line items that are biggest or easiest to change.
  • Measure. VE judges proposals on life-cycle cost and performance. Cost cutting judges them on first cost.
  • Timing. VE is planned into design. Cost cutting is a reaction to a tender result.
  • Outcome. VE can make a building cheaper and better at once. Cost cutting usually makes it cheaper and worse, with the cost showing up later in operations, maintenance or tenant complaints.

Sometimes a project needs scope reduction. That's a legitimate decision, but it should be made openly as a scope decision, not presented as value engineering.

How to evaluate VE proposals

A VE study produces a list of proposals, each with a claimed saving. Not all of them should be accepted. In FHWA's survey of fiscal year 2017, state transportation agencies carried out 160 VE studies that produced 1,451 recommendations, of which 636 were approved, about 44%. The approved recommendations were valued at roughly $1.05 billion against about $6.6 million in study costs. The method pays off, but only because someone sorted the good proposals from the weak ones.

For each proposal, an owner should ask:

  • Is every required function still delivered? Check against the owner's project requirements, not just the drawings.
  • What's the life-cycle effect? A cheaper roof, mechanical unit or flooring can cost more over 20 years in energy, maintenance or early replacement. Our guide to life-cycle cost analysis explains how to compare them.
  • What does it cost to implement? Redesign fees, coordination, permit revisions and schedule time all come off the headline saving.
  • Who carries the risk? A substitution proposed by a contractor can shift design responsibility, warranty or performance risk. Treat it like a change order, with the design team's review.
  • Is the saving real? Confirm it with the cost consultant, not just the proposer.

The Whole Building Design Guide recommends that contractor-proposed VE changes during construction be evaluated from life-cycle and liability perspectives, with the design team involved, and handled like change orders, including their effect on schedule and productivity. Our guide to managing change orders covers that process.

Headline versus net savings on four illustrative VE proposals Four illustrative proposals. Simplify structural grid: headline 250 thousand, net 210. Punched windows on one elevation: headline 420, net 390. Lower-efficiency rooftop units: headline 180, but a 260 thousand life-cycle penalty makes it a net cost of 90. Polished concrete back-of-house: headline 90, net 105. The headline saving isn't the real saving Illustrative VE proposals, $ thousands −$150k $0k $150k $300k $450k Simplify structural grid Simplify structural grid: headline saving $250k $250k Simplify structural grid: net saving $210k $210k net Punched windows on one elevation Punched windows on one elevation: headline saving $420k $420k Punched windows on one elevation: net saving $390k $390k net Lower-efficiency rooftop units Lower-efficiency rooftop units: headline saving $180k $180k Lower-efficiency rooftop units: net cost $90k −$90k net Polished concrete back-of-house Polished concrete back-of-house: headline saving $90k $90k Polished concrete back-of-house: net saving $105k $105k net Headline first-cost saving Net after implementation and life-cycle cost
Illustrative example. Net = headline saving, less redesign and implementation cost, plus or minus the present value of 20-year operating and replacement effects. The highlighted proposal looks good at tender and loses money over the life of the building. Chart by Benjamin R. Consulting.
View the data
ProposalHeadline savingImplementationLife-cycle effectNet
Simplify structural grid$250k-40k+0k+210k
Punched windows on one elevation$420k-60k+30k+390k
Lower-efficiency rooftop units$180k-10k-260k-90k
Polished concrete back-of-house$90k-5k+20k+105k

VE and the delivery model

How value engineering works in practice depends on how the project is being delivered.

Design-bid-build. The owner controls the design until tender, so the owner controls VE. This is the model where an early, independent study is easiest to run and has the most effect. After award, VE ideas usually come from the contractor as substitution requests, and the owner has to evaluate them one at a time.

Construction management and early contractor involvement. Bringing a contractor in during design gives the VE team real pricing and constructability knowledge, which is a major advantage. The risk is that "VE" becomes a running list of substitutions that favour the contractor's buying or methods. Keep function analysis and the owner's requirements at the centre.

Design-build. Once the design-builder is contracted, savings from design changes often belong to the design-builder unless the contract says otherwise. Owners who want VE to benefit them should hold a study on the reference design before procurement, and set out in the contract how later savings are shared. Get legal advice on that wording. Our guide to design-build for owners covers the contract model.

What owners should do

  1. Plan VE into the design schedule. Hold the main study at concept or schematic design, with an optional second study during design development.
  2. Insist on function analysis. A study that goes straight to a list of cheaper materials isn't VE.
  3. Use an independent facilitator, ideally a Certified Value Specialist, with designers in the room but not running it.
  4. Evaluate every proposal on life-cycle cost and implementation cost, not on headline first-cost saving.
  5. Call scope reductions what they are, and record them as owner decisions.

The bottom line

Value engineering is one of the best-value exercises an owner can run, and one of the most misused. Held early, with real function analysis and honest evaluation, it improves the building and its budget at the same time. Held late, as a reaction to a high tender, it usually becomes cost cutting with a nicer label. The difference is mostly timing, and timing is the owner's decision.

Planning a VE study, or reviewing a list of VE proposals? Book a 30-minute call with Benjamin R. Consulting.

Sources: SAVE International, About Value Methodology; Value Analysis Canada, Value Analysis Definitions; National Institute of Building Sciences, Whole Building Design Guide: Value Engineering; U.S. Federal Highway Administration, Value Engineering FAQs; FHWA, Value Engineering Survey for Fiscal Year 2017. The proposal evaluation example is illustrative. This article is general information, not financial or legal advice. Get legal advice on your contract and specific circumstances.

← All insights

Have a program that's slipping, or about to start?

Book a 30-minute call. We'll tell you where your schedule and budget are exposed, and what an owner's rep would change, before you commit to anything.