Toronto’s best office space is filling up, and that changes how tenant improvement (TI) projects should be planned. With premium availability falling and almost no new towers coming, more tenants will be fitting out older or less familiar buildings on tighter move-in dates. Fit-out costs are still rising too.
What happened
Three Q3 2026 market reports now point the same way. Altus Group puts national office availability at 15.1%, down 110 basis points from a year earlier. Toronto also sits at 15.1%, down 190 basis points. The bigger move is in Class A space: downtown Class A availability fell 390 basis points to 11.2%, and midtown Class A fell 730 basis points to 14.1%. In the Financial District, Class A availability is down to 9.2%, and downtown Class A gross asking rents averaged $60.72 per square foot.
Newmark’s figures, reported by Connect CRE on November 5, show the same squeeze from the other side. Leasing in the financial core fell 80% in Q3 to about 253,000 square feet, and Newmark says the cause is limited supply rather than weaker demand. Vacancy in the core is 7.5%, and Class A vacancy is just 5.6%. Leasing outside the financial district rose 16% from the previous quarter, with Downtown West and Downtown North picking up demand. CBRE counts only 12 downtown blocks of more than 100,000 square feet still available, down from 26 in summer 2025.
New supply will not ease this soon. Downtown Toronto has about 302,000 square feet of office under construction, none of it in the financial core. Altus describes the national pipeline of 1.7 million square feet as near a historic low.
Costs are moving too. JLL’s 2026 fit-out cost guide puts Canadian office fit-out increases at 3% to 4% this year. It says mechanical and electrical work makes up about 29% of a typical fit-out, and security, IT and audiovisual about 10%, with that technology share rising 8% year over year across the region.
View the data
| Submarket | Q3 2025 | Q3 2026 | Change |
|---|---|---|---|
| Downtown Class A | 15.1% | 11.2% | −390 bps |
| Midtown Class A | 21.4% | 14.1% | −730 bps |
What it means for your project
The move-in date becomes the hard constraint. When good space is scarce, tenants sign later in the process and landlords have other prospects waiting. That leaves less room for design, permits and construction between lease signing and occupancy, while the old lease or sublease end date stays fixed. On most TI projects, the real schedule risk sits at the front end: approvals, landlord reviews and long-lead orders, not the drywall.
Spillover space means more unknowns. As demand moves into Downtown West, Downtown North, midtown and Class B buildings, more fit-outs will land in older space. That brings base-building questions earlier: mechanical capacity, electrical service, sprinkler layouts, washroom counts and accessibility upgrades. Each one can become a change order if nobody checks it before the design is fixed.
For owners and landlords, the work letter is your project charter. In a market tilting toward landlords, expect more attention to who pays for what. Clear definitions of base-building work versus tenant work, review periods and allowance draw rules protect both sides. A vague work letter usually costs the landlord time and goodwill later, even when it looks like leverage at signing.
For tenants, the allowance is only part of the budget. With technology and mechanical-electrical work making up roughly 40% of a typical fit-out, the items that most often blow budgets are the ones least visible at lease signing. Furniture, IT, audiovisual, moving costs and soft costs sit outside many allowances.
For contractors and designers, compressed schedules reward early involvement. Teams brought in before the lease is signed can test the space, flag base-building gaps and price long-lead items. Late engagement on a fixed move-in date tends to turn into acceleration costs and disputes that nobody budgeted.
View the data
| Component | Share of fit-out cost |
|---|---|
| Mechanical and electrical | 29% |
| Security, IT and AV | 10% (median +8% year over year) |
| All other work (remainder) | 61% |
What to do now
- Do a base-building check before you sign. Have the mechanical, electrical and life-safety capacity of the space reviewed against your planned layout and headcount, and attach the findings to the lease negotiation.
- Build the schedule backward from move-in. Start from the occupancy date and work back through IT cutover, furniture, construction, permits, landlord reviews and design. Our Toronto commercial permit timeline helps size the approval step.
- Order long-lead items early. Release AV, security, specialty mechanical units and electrical equipment as soon as the design allows, and track them on the schedule. See our long-lead procurement guide.
- Budget the whole project, not just the allowance. Include FF&E, technology, moving, fees, permits and a contingency, and carry escalation of at least the 3% to 4% JLL reports for Canadian fit-outs this year. Our FF&E coordination guide covers who supplies what.
- Agree on decision rights early. Name one decision-maker each for the tenant, the landlord and the builder, with set turnaround times for drawings, submittals and changes.
Planning an office move, a fit-out or a landlord work program in the GTA? Book a 30-minute call and we’ll help you test the schedule, budget and work letter before you commit.
Sources: Altus Group: Canadian office market update, Q3 2026 (updated October 21, 2026); Altus Group: Toronto CRE market update, Q3 2026 (updated October 29, 2026); Connect CRE: Financial core leasing drops 80% in Toronto as premium offices fill up (November 5, 2026), citing Newmark and CBRE; JLL: Geopolitical headwinds and structural labor constraints reshape North America office fit-out costs (May 13, 2026); JLL: U.S. and Canada Office Fit-Out Costs Guide 2026. Charts and cover: Benjamin R. Consulting.