Resources / Cost benchmarks / Warehouse Construction
GTA construction cost · 2026

Warehouse construction cost per sq ft in Toronto

Industrial warehouses in the Greater Toronto Area, hard cost only.

2026 GTA range$75–$180per sq ft, hard cost

Short answer (November 2026): Warehouse construction in the GTA costs $75–$180 per sq ft in hard costs, before soft costs, contingency and HST (Altus Group 2026 Canadian Cost Guide). For example, a warehouse of 200,000 sq ft comes to $15.0M – $36.0M in hard cost.

Worked example

A warehouse of 200,000 sq ft

Hard cost (200,000 × $75–$180)$15.0M – $36.0M
Soft costs at 20%$3.0M – $7.2M
Contingency at 10%$1.8M – $4.3M
Indicative total$19.8M – $47.5M

Included: the building above grade, including foundations.
Not included: GST/HST, site development, parking, land and financing. Soft costs and contingency above are illustrative assumptions; change them in the calculator.

Source: Altus Group, 2026 Canadian Cost Guide (GTA hard costs, CAD per sq ft), used with permission. Ranges are indicative; your site, scope and procurement route will move the number. See all 17 building types →

Your budget check
$19.8M – $47.5M
Get a detailed estimate review